Cost of Capital in Regulation: 10 Hot Topics

Quick View

The cost of capital decides about half the revenue of a regulated energy network, and a one percentage point change in it moves that revenue by 8.2 per cent. The Australian Energy Regulator and, in New Zealand, the Commerce Commission have largely settled their methods and chosen continuity over change, though the Australian draft instrument of May 2026 does cut equity beta from 0.6 to 0.55.

What remains contested is narrower but still live: how to reflect climate objectives, how to cope with a shrinking set of listed comparator firms, how to fund a step change in investment, and how to estimate the market risk premium. The sharpest lesson of the past decade, though, is institutional rather than technical. Abolishing merits review in Australia changed regulatory behaviour more than any parameter ever did.

Key Takeaways

  • The stakes are large. A one per cent change in the cost of capital shifts regulated revenue by 8.2 per cent. On Australian electricity network revenues of $12 billion in 2022, that is about $1 billion.
  • The debate has narrowed, not closed. Approaches in Australia and New Zealand have settled, and the AER’s 2023 Rate of Return Instrument concluded that minimising change itself promotes the stability and predictability that supports efficient investment.
  • Climate objectives have entered the frameworks without changing the numbers. The NZCC’s 2023 Input Methodologies review found no specific cost of capital adjustment was needed.
  • Merits review cost consumers $6.5 billion before it was abolished. Reviews were sought on 62 per cent of decisions and no variation ever reduced revenue.
  • Removing it changed the culture. Powerlink’s 2022 determination, built on three years of consumer engagement, was accepted with a revised proposal lodged two weeks early.

The cost of capital is of major importance for infrastructure and utility businesses because they are capital-intensive. The Australian Energy Regulator (AER) estimates that the return on capital is typically about half of the total revenue of the electricity and gas networks it regulates.

Furthermore, small changes in the cost of capital lead to very large changes in regulated revenues. The AER estimates that a 1% change in the cost of capital results in an 8.2% change to regulated revenues. Regulated revenues for electricity networks in Australia were $12 billion in 2022, so a 1% change in the cost of capital would shift revenue by about $1 billion.

Consequently, estimates of the cost of capital are strongly contested. Consumers and regulated businesses try to persuade regulators to employ lower or higher values. This has generated debate across almost all elements of the cost of capital and there is rich and extensive literature on the subject, including litigation in the courts.

In more recent times (at least in Australia and New Zealand), the field of debate has narrowed as approaches have become more settled. There is still active engagement on a range of hot topics including:

  1. Climate change – Energy is at the centre of climate change action. Governments have introduced new emission reduction objectives into regulatory frameworks. How are regulators implementing these objectives in cost of capital and regulatory determinations more broadly?
  2. Stability and predictability of approach – Energy utilities are highly valued for their stable and predictable returns. How do regulators take this into account in their decision-making?
  3. Reasonableness checks – Regulators typically build up their cost of capital by applying models, data, and parameters. How do regulators know if the outcome is reasonable?
  4. Diminishing set of publicly listed comparator firms – Observing market outcomes is important for determining an appropriate cost of capital. How are regulators adapting to the diminishing set of comparator firms?
  5. The term for estimating the cost of equity – The expected cost of equity varies depending on the investment horizon. Should regulators match the term of the regulatory control period or use a longer period reflecting the life of the underlying assets?
  6. Accommodating large new investment – To incorporate large-scale renewable energy projects, large augmentations of existing networks are needed. How do regulators factor these new investments into their cost of capital decisions, especially the cost of debt?
  7. The market risk premium – The data and models for estimating the market risk premium are not very good. What methods should regulators use, and should they anticipate a relationship between the market risk premium and interest rates?
  8. Stranding risk for gas networks – In the face of emission reduction actions, there is an expectation that the use of gas will decline. How do regulators factor in stranding risk?
  9. Competition for the right to supply – Competition is always better than regulation where feasible. With climate action leading to large new transmission links, it is possible to open the construction and operation of these links to competition. How are regulators facilitating this competition, and how can they use the information from the auctions in their cost of capital processes?
  10. Merits review – Good in theory, but bad for consumers and bad for everyone else (except the lawyers). What is the experience with merits review?

Table 1: The three decisions this paper draws on. Three regulators, three recent reviews, and three different starting points on several of the questions that follow.

Three regulators, three recent reviews, and three different starting points on several of the questions that follow.

RegulatorDecisionPublished
New Zealand Commerce Commission Input Methodologies review, and the cost of capital topic paper December 2023
Australian Energy Regulator Rate of Return Instrument, and the explanatory statement February 2023
Ofgem Network price controls 2021–2028 (RIIO-2) and RIIO-ED2 2020 and 2022

Source: as published by each regulator, linked above.

Why it matters. Where the three diverge is as informative as where they agree. All three reviewed the same evidence within roughly three years of each other and reached different answers on the term of the risk-free rate, the treatment of new investment and the use of cross-checks, which is the strongest indication that these questions turn on judgement rather than on data.

Which topics are most contested?

The ten below, chosen because they are where regulators, networks and consumers are still actively disagreeing. Others would pick differently.

There are many topics that could be included in the top 10, and different analysts are likely to have different choices. The following are the topics that seem most important and relevant in my view.

1. How are regulators putting climate objectives into cost of capital decisions?

So far, not by changing the numbers. New Zealand and Australia have both written climate objectives into their frameworks, but neither regulator has adjusted the cost of capital in response, preferring to rely on flexibility elsewhere in the determination.

Many countries now include climate change objectives in their utility regulation. In New Zealand, the Climate Change Response (Zero Carbon) Amendment Act (the Zero Carbon Act) applies. The NZCC explicitly considered this legislation in its 2023 review of the Input Methodologies.

The NZCC considered this aspect from two perspectives:

In conclusion, the NZCC decided that specific adjustments to the cost of capital were not necessary. Instead, it pointed to the flexibility in the regulatory determinations to respond appropriately. It highlighted adaptability in demand and expenditure forecasts (including expenditure to increase resilience) and pass-through mechanisms and re-openers. It did make some adjustments to increase the flexibility available in these mechanisms.

In Australia, the National Electricity, Gas and Retail Laws were amended in September 2023 to introduce an energy emissions objective. The addition is included in section 7(c):

The objective of this Law is to promote efficient investment in, and efficient operation and use of, electricity services for the long term interests of consumers of electricity with respect to:

(a) price, quality, safety, reliability and security of supply of electricity; and

(b) the reliability, safety and security of the national electricity system; and

(c) the achievement of targets set by a participating jurisdiction:

(i) for reducing Australia's greenhouse gas emissions; or

(ii) that are likely to contribute to reducing Australia's greenhouse gas emissions.

The AER’s most recent decisions were almost finalized before the legislation came into effect, but the amendments were anticipated in the proposals it received and its decisions. The results are most evident in forecasting and resilience expenditure.

2. How much weight do regulators give to stability and predictability?

Enough that it can be a reason not to change. The AER conducted a full review of its rate of return approach and concluded that continuing it was the better course, on the grounds that minimising change itself supports efficient investment.

It is common to see different regulators taking different approaches to key elements of the cost of capital. At times these differences can be quite material. Nevertheless, once an approach is employed there is considerable momentum to continue the chosen approach. The AER provides a clear example of this momentum. In its process, both consumers and regulated businesses submitted there should be a “high bar for change”. The AER went on to explain the outcome of its considerations as follows:

We did not come to this process with the expectation of making only minimal changes. We have undertaken an extensive and open process, exploring all aspects of the rate of return in detail. As we progressed through our review, we found the approach in the 2018 Instrument was supported by data and finance principles…

… NEO and NGO are best advanced by largely continuing our current approach. Minimising change is likely to promote stability and predictability and, therefore, efficient investment. We do not consider the bar for change has been met for material changes to our approach.

Regulated utilities are attractive to investors because they are stable, low-risk businesses that offer consistent revenues and returns. This preference for stability extends to the regulatory framework and approach.

3. How do regulators know whether their cost of capital is reasonable?

They cross-check it, while accepting that the cross-checks are weaker than the estimate they test. The data behind them is no better than the data behind the components, and the indicators are heavily influenced by things other than the cost of capital. Cross-checks nonetheless sit at the centre of decision making, and have been reviewed by the courts.

Typically, when regulators set the cost of capital, they do so by exercising regulatory judgment about a range of individual inputs, which are then brought together to generate a result. This is most prominent in the cost of equity, where it is not possible to observe expectations directly.

Consequently, once the result is derived, regulators tend to want to step back and ask themselves whether the result seems reasonable. However, there are considerable difficulties in assessing overall reasonableness. Firstly, the data available is no better (and more likely worse) than the data used to estimate the individual components. Secondly, and more importantly, indicators of reasonableness are heavily influenced by factors outside of the cost of capital. For example, the profitability of regulated businesses depends on the impact of incentive schemes and the ability to outperform the regulator’s opex and capex determinations. Therefore, any use of reasonableness checks is subject to a high degree of judgment.

Nevertheless, reasonableness checks play a central role in regulatory decision making. In 2012, the NZCC undertook a range of reasonableness checks of its final WACC. These checks were then reviewed by the New Zealand High Court on appeal. The High Court observed that:

The comparative information against which the Commission tested its WACC estimates comprised:

(a) yields on five-year Government stock and BBB+ corporate debt;

(b) estimates of the long-run historical returns earned by New Zealand investors on investments of average risk (over the period 1900–2009);

(c) estimates of future returns expected by New Zealand investors on investments of average risk;

(d) estimates of post-tax WACC in other regulatory contexts especially in New Zealand, Australia and the United Kingdom;

(e) independent estimates of the post-tax WACC for New Zealand monopolies; and

(f) estimates of the post-tax WACC using other approaches including the classical CAPM.

The Court then went on to conclude that the Commission’s cost of capital satisfied the reasonableness test, but the appellants would not if they were successful:

We did not come to this process with the expectation of making only minimal changes. We have undertaken an extensive and open process, exploring all aspects of the rate of return in detail. As we progressed through our review, we found the approach in the 2018 Instrument was supported by data and finance principles…

… When we consider our decision in the round, the approach in the 2018 Instrument has delivered outcomes that are consistent with the relevant risks. As such, we think the NEO and NGO are best advanced by largely continuing our current approach. Minimising change is likely to promote stability and predictability and, therefore, efficient investment. We do not consider the bar for change has been met for material changes to our approach.

Australian Energy Regulator, Rate of Return Instrument: Explanatory Statement, 24 February 2023, pages 9 to 10

Similarly, the AER undertook substantial cross-checking in its 2022 rate of return Instrument process. The cross-checks included: regulated asset base (RAB) multiples, financeability tests, scenario testing, historical profitability, investment trends, other regulators’ rate of return and analysts’ discount rates. The AER concluded:

We have explored a range of measures that might provide some insight into the suitability of our overall rate of return. All of these measures suffer limitations, but collectively may provide a sense-check of our overall outcome.

After reviewing the available cross-checks, a balanced assessment of the performance of the 2018 Instrument leads us to reasonably conclude that the 2018 Instrument has broadly performed adequately.

Australian Energy Regulator, Rate of Return Instrument: Explanatory Statement, 24 February 2023, page 24

Among the cross-checks, RAB multiples are the most controversial, with some participants arguing that they have no value while others say they have great value. In respect of RAB multiples, the AER concluded:

Overall, our further investigation leads us to conclude that our current and expected rates of return are at least sufficient (as part of the overall regulatory compensation to investors) and that the allowed return has not been below investor expectations.

Australian Energy Regulator, Rate of Return Instrument: Explanatory Statement, 24 February 2023, page 26

The AER observed that cross-checks have also been employed by Ofgem and Ofwat:

For example, Ofgem uses the following cross-checks for its cost of equity estimate:

  • Modigliani-Miller cost of equity inference (weighted average cost of capital cross-check)
  • market-to-asset ratio (MAR) implied cost of equity
  • unadjusted offshore transmission owner (OFTO) implied equity internal rate of return (IRR)
  • adjusted OFTO implied cost of equity
  • unadjusted investment managers’ total market return (TMR) cost of equity
  • unadjusted infrastructure fund implied equity IRR
  • CAPM with 0.9 equity beta and investment managers’ TMR.

However, in its most recent decision, Ofgem made no adjustment to the rate of return based on the findings of cross-checks. Further, Ofgem’s latest draft decision (ED2 from June 2022) shows that CAPM is used without adjustment even though cross-checks supported lower values, stating that: ‘…we do not adjust the results […] because we are mindful that no cross-check is perfect, and we are confident that CAPM should remain the primary model.’

The Water Services Regulation Authority in the UK (Ofwat) has recently discussed the use of cross-checks in its draft methodology for PR24, stating that it intends to ‘set the allowed return on equity on the basis of the CAPM [and does] not envisage departing from the CAPM-derived estimate of the allowed return, unless there is strong and compelling evidence from market-based cross-checks.’ Further, Ofwat notes that ‘there should be a high evidential bar for moving away from [a] central estimate [and] expect that any adjustment would be modest and would in any case lie within the endpoints of the CAPM derived cost of equity range.’

Ofwat proposed to use the market-to-asset ratio analysis (that is, RAB multiples) as the main cross-check in determining the allowed cost of equity, noting that ‘[Ofwat does] not envisage departing from the CAPM-derived central estimate of the allowed return, unless there is strong and compelling evidence from market-based cross-checks such as MAR analysis.’

Ofwat’s recently published final methodology for PR24 proposes that there is not ‘sufficiently strong evidence from our MAR-based cross-check to choose a point estimate other than our central CAPM-derived point estimate.’

4. What happens as listed comparator firms disappear?

Regulators fall back on older data or on firms that are less comparable. Australia’s two best comparators, Spark Infrastructure and AusNet, have both been acquired and delisted, and the NZCC’s energy comparator sample fell from 74 companies in 2016 to 51 in its 2023 decision.

In recent years, we have seen a trend where publicly listed utility firms have been acquired by private equity firms and subsequently delisted, resulting in the unavailability of data on their traded equity betas.

Most importantly, in Australia, the two best comparator firms, Spark Infrastructure and AusNet, have been acquired and delisted. Typically, these acquisitions have taken place at values well exceeding the regulatory asset base.

With this diminishing data set, regulators are faced with using increasingly old data or drawing on data from firms that are less comparable, including international firms.

In 2016, the NZCC drew on an energy comparator sample that included 74 companies from New Zealand, Australia, United States, and United Kingdom. In its final decision in 2023, 51 comparator firms were included. The resulting equity betas were like those calculated in 2016.

Unless there is a change in the trend of acquisitions, regulators are likely to face a comparator set that is smaller and less representative. This decline is felt most acutely when estimating equity beta, but also impacts credit ratings and gearing.

The AER has signalled that it intends to undertake further work on the comparator set

We have also engaged on this issue as part of our working paper series, as well as our draft Instrument. Having considered the latest submissions and other relevant evidence before us, our view remains that there are likely considerable complexities around developing an approach using international firms as comparators. In particular, international firms likely have different characteristics and operating and market environments to the regulated ‘pure play’ Australian energy network businesses and, as a result, may not be directly comparable to those we regulate. We intend to undertake work on this issue in advance of the 2026 Instrument, particularly considering the diminishing number of comparators.

Australian Energy Regulator, Rate of Return Instrument: Explanatory Statement, 24 February 2023, page 19

5. Should the cost of equity be estimated over the regulatory period or the life of the assets?

Regulators are split, and both of the most recent reviews decided to stay where they were. The AER considered moving from ten years to five and kept ten; the NZCC came under pressure to adopt the Australian approach and kept matching the regulatory period.

Table 2: The term used to estimate the cost of equity, by regulator

Four Australasian regulators, two answers. Two moved to a ten-year term; the two most recent reviews each decided to stay where they were.

RegulatorTerm usedMost recent position
Australian Energy Regulator 10 years Considered moving to 5 years in 2022 and kept 10
New Zealand Commerce Commission Matched to the regulatory period Kept its approach in the 2023 review, under pressure to adopt the Australian one
Queensland Competition Authority 10 years Departed from its long-standing regulatory-period match in its 2019 Queensland Rail draft decision; approach set out in its rate of return review
Economic Regulation Authority (WA) 10 years Raised the term from five years to ten in the 2022 gas rate of return instrument, 16 December 2022

Sources: as linked in the table. The Western Australian change applies to its gas rate of return instrument.

Why it matters: The direction of travel is towards a ten-year term, but the two regulators that reviewed the question most recently both declined to move, and in the Australian regulator’s case the networks opposed a change that would have had only a small effect on the total return. What they were defending was not the number but the precedent: if this changes, what changes next?

There has been a long-standing question about whether the cost of equity should be estimated based on the length of the regulatory period or a period more consistent with the life of the underlying assets. Regulators have taken different approaches in the past and have changed their approaches. For example, the Queensland Competition Authority and Economic Regulation Authority in Western Australia previously employed a term matching the length of the regulatory period but switched to 10-year terms in 2021 and 2022 respectively.

The AER considered changing from a 10-year term to a 5-year term in 2022, but ultimately decided to stay with a 10-year term. Even though the shift would only have a small impact on the total return (once consequential amendments to other parameters were made), the shift was strongly opposed by regulated networks. The networks indicated their opposition was because the shift would undermine the stability and predictability of the current framework “if the AER makes this change, what other changes might be coming in the future?”.

In its review of its Input Methodologies, the NZCC was under considerable pressure to switch from its practice of matching the term of the regulatory period to match the approaches employed in Australia. Ultimately, it decided to maintain its current approach. The NZCC concluded that:

Using a term for the risk-free rate for debt and equity that is matched to the length of the regulatory period ensures consistency in the way in which debt and equity are estimated:

  • Estimates of the risk-free rate used for expert valuations are used in a different context to WACC estimates.
  • In the IMs merits appeals judgment, the High Court agreed with the principle that “the term of the risk-free rate should be aligned to the regulatory term to avoid over and under compensation.”
  • Several suppliers, with the power to set prices as they see fit and which set their own cost of capital when pricing their services, adopt a term of the risk-free rate that matches their pricing period.

New Zealand Commerce Commission, Part 4 Input Methodologies Review 2023: final decision, cost of capital topic paper, 13 December 2023

6. How do long-term averages cope with a step change in investment?

Badly in principle, and regulators have so far decided not to fix it. A trailing average can sit well below the prevailing cost of debt just as a network needs to raise large new capital, but the AER’s proposed weighted trailing average found almost no support and has been deferred.

There is a tendency among regulators to employ long-term averages in their cost of capital. For example:

  • The AER employs a trailing average cost of debt.
  • Ofgem uses a long-term return on equity.

In respect of the cost of debt, utility businesses typically raise debt in a portfolio that spans several years. This means a relatively small proportion of the total debt falls due for renewal each year. In this way, the business can mitigate its financing risk. However, if the regulator sets the cost of debt at each determination, then the business faces interest rate risk unless it can hedge a large proportion of its debt portfolio during the determination window.

If the regulator employs a trailing average approach where a proportion of the cost of debt is updated each year, then the business faces much less pressure to hedge its interest rate risk. In addition, the trailing average approach tends to smooth variations in interest rates, so consumers face a smoother price path across regulatory periods.

These approaches work fine when regulating a business with a stable regulatory asset base and steady year-on-year capital additions. However, long-term averages can be far from the prevailing cost of capital at points in time. In the current circumstances where very large investments in transmission links are needed to support new renewable generation, investment incentives can be distorted.

In Australia, the NSW electricity business, Transgrid, is in the process of constructing several new links that have the potential to double its regulatory asset base over a short period. The trailing average cost of debt employed by the AER is currently below the prevailing cost of debt and this may inhibit the new investment.

The AER recognized this potential issue in its draft Rate of Return instrument and proposed introducing a weighted trailing average based on expected additions to the capital base. The AER set out detail on how the weighted average would operate. However, there was very little support for making the change from stakeholders, including Transgrid. The AER noted that it expects the change in regulatory asset bases to be gradual, with the new projects going through regulatory investment tests and early stages of construction and this would minimize pressure on the trailing average. The AER intends to undertake further work in advance of the next rate of return instrument.

The NZCC employs a prevailing cost of debt approach and received submissions that it should switch to a trailing average. The NZCC decided to maintain its current approach noting:

  • regulated suppliers can use interest rate swaps to materially hedge their risk-free rate exposure without significant hurdles (see Figure 1 below)
  • it has tools other than the WACC for smoothing prices
  • the trailing average could weaken the signals with respect to new investment in infrastructure and
  • there are practical difficulties in implementing a trailing average

Figure 1: Regulated suppliers’ debt portfolios: tenor against interest rate repricing period, 2022

Before swaps the 23 suppliers are spread across the whole range, with five at 7.5 years or more and a value-weighted average original term of 7.25 years. After overlaying swaps the long end empties: nine sit at 2.5 to 5 years, none above 10.

Source: New Zealand Commerce Commission, Part 4 Input Methodologies Review 2023: final decision, cost of capital topic paper, 13 December 2023. Commission analysis of its 2022 confidential debt survey of 23 regulated suppliers.

Why it matters: This one survey decided a methodology. The case for a trailing average cost of debt rests on suppliers being unable to hedge their interest rate exposure within a determination window. The chart shows they can, and cheaply enough that most choose to. That is why the Commerce Commission kept its prevailing-rate approach rather than following Australia.

7. How should regulators estimate the market risk premium?

There is no agreed method, so most fix a value and revisit it periodically. The AER considered blending historical excess returns with a dividend growth model, found little support, and kept a fixed premium; the NZCC settled on a fixed value.

The market risk premium (MRP) is the most challenging element of the cost of capital for regulators. Part of this challenge is that there are very different potential approaches depending on the cost of equity model or models employed. The major classes of models include:

  • The standard Capital Asset Pricing Model (CAPM). In this model,The MRP is one of three fundamental inputs to determining the cost of equity:
E[ri] = rf + βi(E[rm] − rf)
E[ri]
The expected rate of return on asset i when the price is in equilibrium.
rf
The risk-free rate of return.
βi
A standardised measure of covariance risk, representing the non-diversifiable risk of asset i.
E[rm]
The expected rate of return on the market portfolio, m.
E[rm] − rf
The market risk premium (MRP).

  • The Fama-French three-factor model seeks to determine the cost of equity directly by regressing realized returns against various factors.
  • Dividend growth models (DGM) are a class of models used to compute the implied cost of capital. Given the expected cash flows for an asset and the current price, the internal rate of return that equates the present value of the expected cash flows to the current price gives the cost of capital for that asset. In other words, the cost of capital is backed out from a valuation model. From the derived return on equity, the MRP can then be derived.
  • The Wright approach assumes that the market return is constant and then employs a long run average of that return. The consequence of this method is that changes in interest rates are offset one for one by changes in the market risk premium. Thus, if the risk-free rate drops one percent the market risk premium rises by one percent.

Most regulators employ the CAPM. As such, they need a way to estimate the MRP. A common approach is to set a fixed MRP for a period and revisit it every so often. Under this approach the cost of equity varies one-for-one with the underlying risk-free rate. This contrasts with the Wright approach, where the cost of equity is fixed and does not move with the risk-free rate.

The AER has considered how to estimate the MRP. The approaches it has considered include historical excess returns, DGMs, surveys, conditioning variables and total market returns. In its draft decision it considered using a blended approach with an estimate derived 50% from historical excess returns and 50% from the 3-stage DGM. There was little support from stakeholders for this approach, so the AER continued with a fixed MRP for the life of its rate of return instrument.

The NZCC uses three main approaches to estimating the MRP including:

  • studies of historic returns on shares relative to the risk-free rate;
  • surveys of investors asking them to state their expected rate of return for the overall market; and
  • empirical estimates of the MRP from share prices and expected dividends.

The NZCC then determined a fixed tax-adjusted market risk premium of 7.0% for its Input Methodologies.

Professor Aswath Damodaran publishes an annual update for estimating the equity risk premium that provides further details.

The Independent Pricing and Regulatory Tribunal in NSW (IPART) uses a blended approach which estimates the cost of equity as the midpoint between its estimates of the current and historic cost of equity. The historic cost of equity employs a historical estimate of excess returns as the MRP. The current cost of equity uses the median value of the MRP derived from six methods:

  1. Damodaran 2013 method
  2. Bank of England 2002 method
  3. Bank of England 2010 method
  4. Bloomberg method
  5. SFG, now Frontier Economics, analysts forecast method
  6. SFG, now Frontier Economics, market indicator method.

The first four of these methods are variations of the DGM. They differ in detail, but all infer a forward-looking market average return on equity based on expected dividends.The fifth is another variation of the DGM, which uses stock market analysts' forecasts for individual stocks and a dividend discount model. The sixth method uses four economic indicators to derive an indirect estimate of the MRP.

8. How do regulators handle the risk that gas networks are stranded?

By returning capital earlier, and the courts have upheld it. The NZCC shortened asset lives for gas pipelines and the High Court of New Zealand dismissed the appeal against it, concluding that stranding risk had to be addressed somewhere in the framework.

Controversially, in its 2022 Input Methodologies decision, the NZCC allowed for the shortening of asset lives for gas pipelines, in effect, bringing forward depreciation to reduce asset stranding risk. This decision was appealed by the Major Gas Users’ Group to the High Court of New Zealand. The appeal was dismissed in favour of the NZCC’s approach. The Court concluded that stranding risk needed to be addressed somewhere within the regulatory framework. Typically, for a firm in a workably competitive market, that risk would be compensated up-front through expected returns. However, in the case of regulated gas networks, that approach is not feasible, and some ex-post accommodation is required. The NZCC’s approach of an early return of capital was viewed as reasonable.

The Court considered a range of interesting questions including: Is stranding risk already addressed through the weighted average cost of capital component – or otherwise provided for in the input methodologies? Is there provision for asymmetric risk in the WACC? Is there double counting? And is the 2022 Input Methodologies Decision premature?

Like the NZCC, the AER has introduced a degree of accelerated depreciation for gas pipelines. In the case of Evoenergy in the Australian Capital Territory, the AER concluded that accelerated depreciation via shorter asset lives was warranted:

In light of the elevated risk of network closure and a substantial reduction in demand, we consider our final decision is a prudent and responsible first step to protect the long-term interests of Evoenergy’s gas consumers from asset stranding risk.

Australian Energy Regulator, Final decision: Evoenergy access arrangement 2021–26, Attachment 4: Regulatory depreciation, 30 April 2021

The AER noted that it would not be prudent for the network owner to add substantial new discretionary investment capital in the current environment.

But what if gas network closure advances far more rapidly than anticipated? It depends on whether customers are locked in or can exit the network. If customers are locked in, they will pay higher prices to recover the outstanding capital over a shorter period. On the other hand, if demand and customer numbers decline, which is more likely, the remaining customers will face rapidly increasing prices. At this point, it may no longer be possible for the network to charge the regulatorily determined prices because it will accelerate the “death spiral”. Options at this stage include deregulating the network, leaving the risk to be managed by the equity holders, or government intervention to support customers or the asset owners.

9. Can competition replace regulation for new transmission links?

Where the asset is discrete enough to tender, yes, and the auction reveals a cost of capital as a by-product. The UK has auctioned offshore transmission rights and New South Wales is tendering its first renewable energy zone network.

With new large-scale links being built to support renewable energy generation, there is an option for these links to be built and operated through a competitive tender process. Provided the competitive tender is robust, this is an excellent opportunity to avoid the need for regulation altogether. Further, the information revealed in these processes could be used by regulators to cross-check the cost of capital they are employing in their regulatory decisions.

There are 2 recent prominent examples: UK offshore wind transmission and NSW renewable energy zones (REZ).

In the UK, the right to build, own and operate offshore wind transmission lines has been auctioned. From the auction results, it is possible to estimate an implied cost of capital. Ofgem has published the results of its analysis.

We previously referred to OFTO bids in December 2018, May 2019 and July 2020 where we used OFTO bids to derive the average implied equity IRR (nominal, post tax). We acknowledge that there are risk differences between DNOs and OFTOs. OFTOs are not subject to cyclical price controls (such as RIIO-ED2) that apply to the onshore electricity distribution assets. However, we believe that this cross-check is valuable because it relates to electricity network assets, where Ofgem issues and modifies licences, as it does for the electricity distribution sector.

Ofgem, Consultation, RIIO-ED2 Draft Determinations – Finance Annex, 29 June 2022, pages 45 to 46

Figure 2: Offshore transmission owner auctions: average nominal post-tax equity IRR. The implied return falls 3.7 percentage points across six rounds, from 10.2% to 6.5%, with the sharpest step between 2015-16 and 2017-19. Twenty-six projects in total.

The implied return falls 3.7 percentage points across six rounds, from 10.2% to 6.5%, with the sharpest step between 2015-19. Twenty-six projects in total. These are unadjusted figures, embedding gearing of 80 to 90 per cent rather than the 60 per cent notional level.

Source: Ofgem, RIIO-ED2 Draft Determinations – Finance Annex, 29 June 2022, Figure 3, page 46. Cost of equity cross-checks derived from offshore transmission owner bids.

Why it matters: Almost every input to the cost of equity is a modelled estimate that cannot be checked against anything. This one can: it is what investors actually bid to own and run regulated network assets, which is why Ofgem uses it as a cross-check. The steady decline as risk-free rates fell over the same period is also evidence against the Wright approach, under which the total market return would have held flat. It did not.

In NSW, EnergyCo is leading the development of the renewable energy zone (REZ) transmission network infrastructure as the Infrastructure Planner. EnergyCo is responsible for developing and overseeing the planning and approval processes for the REZ network infrastructure. Its first major project is the Central-West Orana REZ which will be serviced by new transmission network infrastructure, including transmission lines and energy hubs. EnergyCo is currently running a competitive tender process to appoint a Network Operator to design, build, finance, operate and maintain the REZ transmission network.

10. What did merits review actually do?

It became routine, cost consumers $6.5 billion, and never once reduced revenue. Reviews were sought on 32 of 51 decisions between 2008 and 2016, amendments in 2013 failed to change that, and the regime was abolished.

While merits review is not strictly a cost of capital issue, its influence on cost of capital is of the highest importance.

Regulatory determinations embody the exercise of judgment. Otherwise, regulatory outcomes could be coded in legislation and there would be no need for regulators. When exercising judgment, it is possible for regulators to err. Merits review provides a mechanism for regulatory judgements to be tested and corrected if made in error. On face value, this logic is compelling. However, in practice, merits review has the potential to result in highly undesirable outcomes. This was the case in Australia, and ultimately led to the removal of merits review.

In Australia, the use of merits review of regulator decisions was commonplace. Between 2008 and 2016 reviews were sought on 32 out of 51 regulatory decisions (62%). Even after amendments were made in 2013 to rebalance and minimise reviews, 12 out of the 19 decisions from 2015 onwards were taken to review (63%). Of all the matters that were varied or remitted back to the primary decision maker, none resulted in a decrease in revenues for the regulated business compared to the original decision.

Figure 3: AER regulatory decisions appealed under limited merits review, 2008 to 2016. Appeals were routine throughout: 32 of 51 decisions. The 2014 reforms, designed to curb them, made no difference, 12 of the following 19 decisions were still taken to review.

Appeal was routine throughout, sought on 32 of 53 decisions, or 60 per cent. The 2013 amendments, meant to curb it, made no difference: of the 19 decisions that followed the reforms, all of them falling from 2015, 12 were taken to review.

Source: Australian Energy Regulator, Review of the limited merits review framework, October 2016, Figure 2.2.

Why it matters. Read this alongside one fact from the text: of all the matters varied or remitted, none ever reduced revenue. An appeal was therefore a free option, costless on the downside and potentially worth hundreds of millions on the upside, so appealing was the rational default rather than a response to genuine error. The chart shows the 2013 attempt to fix that failing, which is what turned the argument from reform to abolition.

The practical lack of downside risk in seeking a review, coupled with the potential for significant increases in revenues, means that service providers pursue limited merits reviews of our decisions as a routine part of the determination process. …

… Regulatory proposals are commonly drafted in a highly legalistic tone. In some cases, service providers have submitted reports prepared by legal counsel. The focus of the proposals has been diverted from being economically persuasive to being legally defensible on appeal. It also makes it harder for other stakeholders, without access to lawyers, to engage with the arguments in such submissions.

Australian Energy Regulator, Review of the limited merits review framework, October 2016, page 16.

In the second reading speech on the Bill to abolish limited merits review the Minister noted a range of problems with the framework: 

To date LMR has increased consumer bills by $6.5 billion. … the Council of Australian Governments (COAG) Energy Council reviewed the LMR regime again in 2016. The review found that the 2013 amendments to the regime had largely failed, including that LMR: remained routine; had significant costs to all participants; presented barriers to meaningful consumer participation; led to significant regulatory and price uncertainty; and was failing to demonstrate outcomes that were in the long-term interests of consumers. The COAG Energy Council determined that the LMR regime was still failing to meet its policy intent with the consequence of higher prices for consumers. In the face of escalating energy prices the government is taking action to stop energy networks using the LMR to extract monopoly rents from consumers.

The Hon Josh Frydenberg MP, Minister for the Environment and Energy, second reading speech on the Competition and Consumer Amendment (Abolition of Limited Merits Review) Bill 2017, House of Representatives, 10 August 2017.

Since the removal of limited merits review, the regulatory framework in Australia has fundamentally changed. Instead of regulation being “something that is done to consumers”, regulated networks are undertaking extensive and meaningful engagement with consumers, giving them a real say in the proposals they submit to the regulator.

The Powerlink Queensland electricity transmission decision in 2022 was a watershed moment in the cycle of regulatory determinations. Powerlink approached its determination with the objective of putting forward a proposal that was capable of acceptance by consumers, the regulator, and itself.

In its final decision, the AER noted:

The high-quality nature of Powerlink Queensland’s initial revenue proposal has meant that the final stage of this process, where we assessed its revised revenue proposal, has been non-contentious and a more efficient regulatory process for all stakeholders, including Powerlink Queensland, consumers and the AER.

Australian Energy Regulator, media release on the Powerlink Queensland transmission determination 2022–27, April 2022.

This trend has continued. It is brilliant to see consumers at the centre of the regulatory process rather than lawyers. In the most recent round of regulatory proposals, consumer engagement and influence have been a dominant feature. In almost all cases, the AER has been able to accept the proposals put to it, rather than intervening. 

Table 3: Outcomes of the AER’s most recent regulatory determinations

Six businesses, seven network determinations, all for the 2024–29 period running from 1 July 2024 to 30 June 2029. The draft decisions of September 2023 cut the five mainland proposals by between 0.1% and 6.8%, and allowed TasNetworks more than it had asked for on both networks. The businesses then revised towards those decisions, and the final determinations were published on 30 April 2024.

BusinessNetworkDraft decision revenue ($ million)Difference from the proposal
AusgridNSW electricity distribution9,619.6144.3 (1.5%) lower
Endeavour EnergyNSW electricity distribution5,597.85.6 (0.1%) lower
Essential EnergyNSW electricity distribution6,191.1185.7 (3.0%) lower
EvoenergyACT electricity distribution1,043.734.8 (3.2%) lower
Power and Water CorporationNT electricity distribution1,016.474.7 (6.8%) lower
TasNetworksTasmania electricity distribution1,826.0111.5 (6.5%) higher
Tasmania electricity transmission880.113.2 (1.5%) higher

Source: Australian Energy Regulator, draft decisions on the 2024–29 regulatory proposals, September 2023, and final revenue decisions, 30 April 2024.

Why it matters. Set against Figure 3, this is where the argument now happens. Under limited merits review, 60% of the regulator’s decisions were taken to the Tribunal after it had finished. Here the regulator moved the numbers at draft decision stage, the businesses revised towards it, and the matter ended there, because there is no longer a merits review to take it to. The table cannot settle the counter-reading, that acceptance reflects a low bar rather than better proposals. What it does show is a regulator still reducing five of the seven forecasts before agreement was reached.

Honourable mentions

While not making our top 10, the following issues are worth a mention.

1. Can regulators measure the cost of debt accurately?

It is possible for regulators to very accurately measure and then estimate the forward cost of debt. The AER uses an approach where it obtains details of each debt instrument issued by the private businesses it regulates. This data is sensitive, so the process is conducted in confidence. The AER then publishes a summary of its analysis which shows how the actual cost of debt is tracking against the yield curves it employs for estimating the cost of debt.

This analysis shows that there is a very close correlation between the actual cost of debt and the AER’s estimates.

Figure 4: Energy infrastructure credit spread index against AER cost of debt estimates, June 2015 to June 2023

Both series are twelve month rolling averages of spreads over the swap rate, matched on term. They track each other for most of the eight years, fall together to a trough near 95 basis points at the end of 2021, and climb together to 196 and 183 by June 2023. They part twice, in opposite directions: across 2016 the estimate runs above the index, by about 45 basis points in June 2016, and in late 2020 and early 2021 the index runs above the estimate, by about 20.

Source: Australian Energy Regulator, Rate of Return Annual Update 2023, December 2023, Figure 12, page 29.

Why it matters. The cost of debt is the only major component of the cost of capital that can be checked against what regulated businesses actually pay. The equity beta, the market risk premium and the term are modelled expectations with no observable counterpart, which is the difficulty behind the reasonableness checks discussed earlier. On the one testable parameter, the estimate tracks observed costs closely, apart from two partings: a sustained overshoot across 2016, about 45 basis points at its widest, and a smaller shortfall of about 20 basis points in late 2020 and early 2021.

2. Should a convenience yield be added to the risk-free rate?

This issue arose in a Competition and Markets Authority decision in 2021. Since then, it has been raised in front of multiple regulators, but to date accepted by none. The argument, as put to the NZCC by Oxera, is “in contrast to the highest-quality non-government bonds, government bonds have special properties that create additional demand for these instruments, which pushes the government bond yield to fall below a ‘true’ risk-free rate based on a zero beta asset”.

The proposed solution is to add a convenience yield to the risk-free rate or include high quality non-government bonds in the estimate of the risk-free rate.

The NZCC did not agree to depart from using government bonds to estimate the risk-free rate. It noted:

  • We were not aware of any practitioners in New Zealand that use bonds other than government bonds to estimate the risk-free rate
  • It would not always be possible to find sufficiently liquid corporate bonds with the required credit rating to use to estimate the risk-free rate
  • There are practical problems estimating a convenience yield

New Zealand Commerce Commission, Part 4 Input Methodologies Review 2023: final decision, cost of capital topic paper, 13 December 2023

Similarly, the AER considered a convenience yield in depth and decided not to employ the approach.

3. How should debt and equity be weighted?

The “W” in WACC stands for weighted. Regulators typically estimate the cost of debt and equity separately and then bring them together using a ratio. A common ratio is 60% debt and 40% equity. This ratio has tended to be relatively uncontroversial.

The AER updates its estimate at each rate of return review. The data shows that businesses employ a ratio that is largely stable. The AER received a report from Professor Graham Partington and Stephen Satchell that concluded:

Our discussion and analysis focuses on a number of features of WACC. We argue that WACC does not change a great deal with changes in leverage, largely because there are arbitrages that come into play. Except at extreme levels of leverage, the effects of arbitrage are likely to render the value of the firm relatively invariant to changes in leverage.

Graham Partington and Stephen Satchell, Report to the AER: WACC and Leverage, May 2021.

4. Should regulators run financeability tests?

It is not uncommon to find submissions that advocated for the use of financeability testing. The NZCC concluded:

We consider that financing the preferred path of recovery of investment, the one that best promotes the Part 4 purpose, is primarily the responsibility of suppliers. They have a range of tools for doing so, including reducing dividend payments, or raising debt and/or equity. In addition, we are not aware of a shortage of capital currently in this sector. To the contrary, we continue to see transactions at RAB multiples above one, and improving credit ratings.

New Zealand Commerce Commission, Part 4 Input Methodologies Review 2023: final decisions, 13 December 2023.

5. Does a totex approach help?

The mix of opex and capex used in a regulatory determination is not, of itself, a cost of capital issue. However, the mix has a material impact on cash flow and measures of financeability.

Ofgem employs a totex approach where a total expenditure of opex and capex is determined and the regulated business then has a degree of flexibility in the balance of opex and capex going forward. Under the totex approach, there is a risk that regulated businesses will favour opex over capex to increase cash flows in the short term.

The NZCC received some submissions that carbon reduction required further incentives for capex, such as the totex framework employed by Ofgem. It concluded:

Of the alternative expenditure incentive approaches that we considered, such as a totex approach (including a totex incentive mechanism), our decision is that none better promote our Framework’s overarching objectives than the current expenditure incentive mechanisms.

New Zealand Commerce Commission, Context and summary of final decisions: Part 4 Input Methodologies Review 2023, 13 December 2023, paragraph 4.23.

6. Should new and sunk assets get different rates of return?

A split cost of capital would involve applying different WACC values to existing “sunk” assets and capital on new assets.

The NZCC considered that its approach provides suppliers with incentives to invest without providing for a different WACC. Non-systematic risks can be more appropriately dealt with through measures outside of the WACC.

7. How do regulators handle uncertainty in their own estimate?

The NZCC employs a peculiar approach where it estimates a standard error for the cost of capital and then adjusts the final value of the cost of capital based on its judgement on where the probability of error should sit.

When exercising this judgement, the NZCC considers potential asymmetry in the consequences of setting an incorrect cost of capital.

Setting the WACC too high is expensive for consumers because they pay higher bills. However, setting the WACC too low may result in even higher costs for consumers if it leads to outages. Outages from an unreliable network are expensive for consumers and remediating an unreliable network is likely to take some time.

New Zealand Commerce Commission, Cost of capital topic paper: Part 4 Input Methodologies Review 2023, final decision, 13 December 2023, page 219.

The NZCC ultimately decided to set the cost of capital for electricity business at the 65th percentile (down from the 67th percentile). This approach seems to have had its genesis in a major electricity cable failure into New Zealand’s largest city (Auckland) in 1998. The failure resulted in electricity outages and major disruption for 5 weeks.

8. Should the regulatory asset base be indexed?

Previously, the NZCC did not index the regulatory asset base for Transpower. When the regulatory asset base is indexed, investors receive part of their total return through capital accumulation rather than cash.

The NZCC decided that it would change its approach for Transpower and index the regulatory asset base going forward. It considered “the benefits of indexation (protection from inflation and promoting pricing profiles that are more likely to be consistent with allocative efficiency) justify the change”.

9. Why does inflation forecasting matter?

Estimates of actual and forecast inflation are employed in many places within the regulatory models and cost of capital estimates. The issues are extensive and complex. The AER undertook an extensive review of inflation, publishing its final position paper on the regulatory treatment of inflation in December 2020.

References

  1. Australian Energy Regulator. (2016, October). Review of the limited merits review framework: Submission to the Senate Committee on the Competition and Consumer Amendment (Abolition of Limited Merits Review) Bill 2017. https://www.aer.gov.au/system/files/AER%20submission%20-%20Bill%20to%20remove%20Limited%20Merits%20Review%20-%20Submission%20to%20the%20Senate%20Committee.pdf
  2. Australian Energy Regulator. (2020, December). Regulatory treatment of inflation: Final position paper.
  3. Australian Energy Regulator. (2021, April 30). Final decision: Evoenergy access arrangement 2021–26. Attachment 4: Regulatory depreciation. https://www.aer.gov.au/industry/registers/access-arrangements/evoenergy-access-arrangement-2021-26
  4. Australian Energy Regulator. (2022, April). AER makes final decision on Powerlink Queensland’s electricity transmission revenue proposal for the 2022–27 period [Media release]. https://www.aer.gov.au/news/articles/communications/aer-makes-final-decision-powerlink-queenslands-electricity-transmission-revenue-proposal-2022-27-period
  5. Australian Energy Regulator. (2023, February 24). Rate of return instrument: Explanatory statement. https://www.aer.gov.au/system/files/AER%20-%20Rate%20of%20Return%20Instrument%20-%20Explanatory%20Statement%20-%2024%20February%202023_1.pdf
  6. Australian Energy Regulator. (2023, February). Rate of return instrument 2022: Final decision. https://www.aer.gov.au/publications/guidelines-schemes-models/rate-of-return-instrument-2022/final-decision
  7. Australian Energy Regulator. (2023, February). AER releases final decision on rate of return for regulated energy networks [News release]. https://www.aer.gov.au/news/articles/news-releases/aer-releases-final-decision-rate-return-regulated-energy-networks
  8. Australian Energy Regulator. (2023, September). AER consults on draft decisions for Ausgrid, Endeavour Energy, Essential Energy, Evoenergy, TasNetworks and Power and Water Corporation 2024–29 regulatory proposals [Media release]. https://www.aer.gov.au/news/articles/communications/aer-consults-draft-decisions-ausgrid-endeavour-energy-essential-energy-evoenergy-tasnetworks-and-power-and-water-corporation-2024-29-regulatory-proposals
  9. Australian Energy Regulator. (2023, December). Rate of return annual update 2023. https://www.aer.gov.au/system/files/2023-11/AER%20-%20Rate%20of%20Return%20annual%20update%20-%20December%202023.pdf
  10. Australian Energy Regulator. (2024, April 30). Final revenue decisions balance affordability and required investment [News release]. https://www.aer.gov.au/news/articles/news-releases/final-revenue-decisions-balance-affordability-and-required-investment
  11. Australian Energy Regulator. (2025, August 4). 2026 rate of return instrument review: Discussion paper. https://www.aer.gov.au/system/files/2025-08/AER%20-%202026%20RORI%20review%20discussion%20paper%20-%204%20August%202025.pdf
  12. Australian Energy Regulator. (2026, May 29). Draft 2026 rate of return instrument: Explanatory statement. https://www.aer.gov.au/system/files/2026-05/AER%20-%20Draft%202026%20RORI%20Explanatory%20Statement%20-%2029%20May%202026_0.pdf
  13. Climate Change Response (Zero Carbon) Amendment Act 2019 (NZ).
  14. Commerce Commission. (2022). Input methodologies amendments: Gas pipeline businesses’ asset lives [Decision on accelerated depreciation].
  15. Commerce Commission. (2023, December 13). Part 4 Input Methodologies Review 2023: Final decision. Context and summary of final decisions. https://www.comcom.govt.nz/__data/assets/pdf_file/0033/337677/Part-4-IM-Review-2023-Final-decision-Context-26-summary-paper-13-December-2023.pdf
  16. Commerce Commission. (2023, December 13). Part 4 Input Methodologies Review 2023: Final decision. Cost of capital topic paper. https://www.comcom.govt.nz/__data/assets/pdf_file/0022/337612/Part-4-IM-Review-2023-Final-decision-Cost-of-capital-topic-paper-13-December-2023.pdf
  17. Commerce Commission. (2023). 2023 Input Methodologies review [Project page]. https://www.comcom.govt.nz/regulated-industries/input-methodologies/input-methodologies-for-electricity-gas-and-airports/input-methodologies-projects/2023-input-methodologies-review/
  18. Competition and Consumer Amendment (Abolition of Limited Merits Review) Bill 2017 (Cth). https://www.aph.gov.au/Parliamentary_Business/Bills_Legislation/Bills_Search_Results/Result?bId=r5929
  19. Damodaran, A. (n.d.). Equity risk premiums (ERP): Determinants, estimation and implications [Annual update].
  20. Economic Regulation Authority (Western Australia). (2022, December 16). 2022 gas rate of return instrument: Final decision. https://www.erawa.com.au/access/gas-access/guidelines-and-compliance/gas-rate-of-return-instrument/2022-gas-rate-of-return-instrument-review
  21. Frydenberg, J. (2017, August 10). Competition and Consumer Amendment (Abolition of Limited Merits Review) Bill 2017: Second reading speech [Speech]. House of Representatives, Parliament of Australia.
  22. Independent Pricing and Regulatory Tribunal. (n.d.). WACC methodology: Cost of equity and market risk premium.
  23. Major Gas Users’ Group Inc v Commerce Commission (High Court of New Zealand).
  24. National Electricity (South Australia) Act 1996, Schedule (National Electricity Law), s 7, as amended by the Statutes Amendment (National Energy Laws) (Emissions Reduction Objectives) Act 2023 (SA).
  25. Ofgem. (2020, December). RIIO-2 final determinations: Transmission and gas distribution network companies and the Electricity System Operator. https://www.ofgem.gov.uk/decision/riio-2-final-determinations-transmission-and-gas-distribution-network-companies-and-electricity-system-operator
  26. Ofgem. (2022, June 29). RIIO-ED2 draft determinations: Finance annex [Consultation]. https://www.ofgem.gov.uk/sites/default/files/2022-06/RIIO-ED2%20Draft%20Determinations%20Finance%20Annex.pdf
  27. Ofgem. (2022, November). RIIO-ED2 final determinations. https://www.ofgem.gov.uk/decision/riio-ed2-final-determinations
  28. Ofwat. (2022, July). PR24 draft methodology.
  29. Ofwat. (2022, December). PR24 final methodology.
  30. Oxera. (n.d.). Submission to the Commerce Commission on the risk-free rate and convenience yield [Report for the Part 4 Input Methodologies Review 2023].
  31. Partington, G., & Satchell, S. (2021, May). Report to the AER: WACC and leverage. https://www.aer.gov.au/system/files/Report%20to%20the%20AER%20%E2%80%93%20WACC%20and%20Leverage%20%E2%80%93%20May%202021.pdf
  32. Queensland Competition Authority. (2023). Rate of return review: Updated report. https://www.qca.org.au/wp-content/uploads/2020/11/qca_rate-of-return-review_updated-report_2023.pdf
  33. Wellington International Airport Ltd v Commerce Commission [2013] NZHC 3289 (High Court of New Zealand).

Authors

 What’s next

Featured

This paper has been published on following other platforms

I was delighted that MCC's work was completed on time, and within budget, helping us deliver important changes and improvements, to the benefit of our stakeholders. ​ MCC's report is published on the CCC website.

- Bea Natzler
Team Leader at Climate Change Committee, UK

I am delighted to recommend MCC Economics. Specifically, I worked closely with PJ, who helped us with our Nuclear and CCUS projects. PJ helped us develop new policies and answer questions from our stakeholders. ​​His support helped us deliver important changes and improvements, to the benefit of our stakeholders.

- Gordon Hutcheson
Head of Nuclear Policy at Ofgem, UK

MCC Economics has helped us better understand the most important issues for our stakeholders, including: charges, shareholder returns, debt payments and inflation impacts.

- Leila N. Nasr
Section Head at Department of Energy, Abu Dhabi

I am delighted to recommend PJ and his team at MCC Economics. We've been working together on National Policy Statements to help meet net zero targets for 2030 and 2050. We initially appointed MCC Economics to support us on offshore wind consultation analysis and have recently reappointed MCC Economics to undertake a larger consultation analysis role across all sectors, including hydrogen, CCUS and networks. I can confirm that PJ and his team have shown excellent spreadsheet skills, alongside very good project management, planning and analysis skills, helping us deliver important changes, and continuous improvements, to the benefit of our stakeholders.

- Amy McHugh
Head of Environment in the Energy Infrastructure Planning Policy, UK

I am delighted to recommend PJ and his team from MCC Economics. They helped us with our price controls for Heathrow airport and for NATS (En Route) plc (the air traffic services provider). Specifically, the MCC team helped us deliver important changes and improvements to our financial models and supporting policy documents, to the benefit of our stakeholders.

- Dan Rock
Head of Corporate Finance at CAA, UK

I am delighted to confirm that I worked with PJ on a retail project in 2015. The project helped stakeholders understand electricity costs and charges. Specifically, the project helped us explain to stakeholders, internally and externally, why electricity charges differed across the regions (GB, NI & Ireland). PJ was a key member on the project team, which helped deliver changes and improvements in the understanding of energy retail.

- Kevin Shiels
Director at Utility Regulator, Northern Ireland