Electricity distribution privatisation in Great Britain: the Electricity Act 1989 and the initial price controls

Quick Answer

The electricity distribution networks in England and Wales were privatised in 1990, through the Electricity Act 1989. The industry was restructured on 1 April 1990, and the twelve Regional Electricity Companies of England and Wales were sold in December 1990 at 240 pence per share. The networks were privatised with price controls already embedded in their licences under the RPI−X regulatory framework, which at first limited allowed price increases to inflation, measured by the Retail Price Index, plus a company-specific X factor. Over time, the X factor adopted became negative, reflecting the expectation of efficiency gains that would reduce future price increases.

Key Takeaways

  • The Electricity Act 1989 created the legal framework for privatising electricity supply in Great Britain: a regulator, consumer committees, licensing requirements and vesting powers.
  • England and Wales were restructured on 1 April 1990. The Central Electricity Generating Board was split, National Grid was created and owned at first by twelve Regional Electricity Companies, which replaced the former Area Boards.
  • The twelve Regional Electricity Companies were sold in December 1990 at 240 pence per share, paid in three instalments. The offer was about ten times subscribed, and the House of Commons Library records net proceeds of 7.713 billion pounds.
  • The networks were not left unregulated. Distribution charges for the twelve companies were initially capped at the RPI plus X, with X ranging from 0 to 2.5 percentage points per year and a weighted average of about 1.1. The government said this allowed about 5 billion pounds of network investment.
  • The initial controls later looked generous. The electricity regulator recorded distribution operating profit at 34% of turnover in 1990/91 and between 40% and 43% in each year up to 1996/97, before tighter controls pushed allowed charges down in real terms 
  • Competition was introduced in supply, phased by customer size, while distribution stayed a regulated monopoly. That split remained central in subsequent regulatory reviews. 
  • Scotland and Northern Ireland followed different routes: vertically integrated Scottish companies sold in June 1991, and a separate Northern Ireland restructuring under the Electricity (Northern Ireland) Order 1992.

Scope of this article

This article covers the privatisation and the initial regulatory settlement for electricity distribution around the Electricity Act 1989. Strictly, the 1989 act was the enabling legislation. Vesting and restructuring came at the end of March and on 1 April 1990, and the twelve England and Wales Regional Electricity Companies were sold in December 1990.The article focuses on the immediate post-privatisation period, before the main review sequence that revised controls from 1995/96 and then from 1 April 2000. Those reviews will be covered in future articles in this series.

Key pre-review timetable

Table 1: Timeline from the Electricity Act 1989 to the first revision of distribution controls in 2000.

Date Event
27 July 1989 Electricity Act 1989 received Royal Assent.
31 March 1990 Government vested the publicly owned electricity supply industry in successor public limited companies.
1 April 1990 England and Wales industry restructured. Central Electricity Generating Board functions split and twelve Regional Electricity Companies replaced the Area Boards.
March/April 1990 First phase of supply competition opened for customers above 1 megawatt, about 30% of the market.
December 1990 The twelve England and Wales Regional Electricity Companies were sold.
June 1991 Scottish Power and Scottish Hydro-Electric sold as vertically integrated companies.
1 April 1994 Second supply-competition phase opened for 100 kilowatt to 1 megawatt customers, about 15% of the market.
Sept 1998 to June 1999 Remaining market below 100 kilowatts, about 55% of the market, opened in stages.
1 April 2000 Existing distribution price controls revised under the 1998 to 2000 review.

When was electricity distribution privatised in Great Britain?

Distribution was privatised operationally in 1990, even though the enabling Electricity Act received Royal Assent on 27 July 1989. The public debate and the law belong to 1989, but investors bought the network shares only after vesting, licensing, capital restructuring and the initial price controls were in place.

The long title of the Act illustrates the breadth of the reform. It provided for the appointment and functions of a Director General of Electricity Supply, created consumer committees, set new rules for supply through electric lines, and determined the vesting of the property, rights and liabilities of the Electricity Boards and the Electricity Council in successor companies.

That legal framework became a new industrial structure on 1 April 1990. In England and Wales, the Central Electricity Generating Board was replaced by Nuclear Electric, National Power, PowerGen and National Grid. The latter was initially owned jointly by the twelve Regional Electricity Companies, until it was floated separately in 1995. The Regional Electricity Companies, in turn, replaced the previous Area Boards.

What did “distribution” mean at privatisation?

At privatisation, distribution meant the local wires monopoly: the regional network of substations, transformers, overhead lines, underground cables and low-voltage assets that carried electricity from the transmission system to homes and businesses. The government described the area supply companies as holding a monopoly on distribution, with National Grid holding the monopoly on transmission.

The Regional Electricity Companies were not, however, pure network companies in the modern sense. Each combined a regional distribution network with a public supply business. They bought electricity through the newly created Electricity Pool, distributed it across their local networks, and sold it to customers. Their generation ownership was restricted, with each company permitted to own no more than 15% of its power generation requirements.

This hybrid structure explains the later pressure to separate supply, metering and distribution. Supply was intended to become competitive, while distribution stayed a regional monopoly requiring continued price regulation.This dual framework was a large reason for the separation of these activities into different businesses later on. 

Who were the twelve Regional Electricity Companies?

The twelve Regional Electricity Companies were Eastern Electricity, East Midlands Electricity, London Electricity, MANWEB, Midlands Electricity, Northern Electric, NORWEB, Southern Electric, SEEBOARD, South Wales Electricity, South Western Electricity and Yorkshire Electricity. Each replaced its corresponding Area Boards and became the regional distribution and public supply companies for its territory.

The regional structure mattered because the networks differed sharply in customer density, terrain, urbanisation and underground assets. The costs and operating risks of serving London were very different from those of serving a rural or semi-rural region. Every later review had to compare these companies while allowing for those inherent differences.

How were the Regional Electricity Companies sold, and how much did the sale raise?

The twelve companies were sold in December 1990 through a fixed-price public offer of the government’s shareholding at 240 pence per share. Payment was made in three instalments: 1 pound at flotation, 70 pence in October 1991, and 70 pence in September 1992. The Commons Library records that the offer was about ten times subscribed and describes it as one of the most popular privatisations of the period.

A number worth reading carefully: the House of Commons Library records net proceeds of 7.713 billion pounds. In January 1991, however, the government told Parliament that the sale would return close to 8 billion pounds in total: a little over 5 billion pounds from the shares and almost 3 billion pounds from debt loaded into the companies before flotation.

These figures should not be treated as separate amounts that can be added together. On the government’s own account, the share proceeds were about 5 billion pounds, so the 7.713 billion figure is best read as the return incorporating both equity and debt, rather than equity proceeds by themselves. Reusing these numbers warrants a verification on its precise basis in the National Audit Office report on the sale (HC 10, 6 May 1992).

The companies’ debt levels were set deliberately before the sale. On 23 July 1990, the Secretary of State reported total debt of 2,843.5 million pounds for the twelve companies plus National Grid, split as 1,942.5 million pounds for the Regional Electricity Companies and 901 million pounds for National Grid.

Were the networks regulated when they were privatised?

Yes. The networks were privatised with price controls already attached. Distribution charges for the twelve companies were capped at the RPI plus a company-specific X factor between 0 and 2.5 percentage points per year, with a weighted average for the sector of about 1.1. At vesting, the controls were set for five years and typically allowed real increases in distribution charges.

The initial formula of RPI plus X is worth distinguishing from the later and more familiar description of RPI minus X. The X factor was set at a positive level upon privatisation to encourage investment, while future price controls prioritised spending efficiency when setting allowances. National Grid’s transmission charges were capped at the RPI alone. The government stated that transmission and distribution represented about 10 and 20% respectively of the final customer price, and that the controls would allow about 5 billion pounds of investment in the capital-intensive distribution network while maintaining security standards.

Figure 1: Share of final customer price at privatisation

10%
Transmission — 10%
20%
Distribution — 20%
70%
Generation, supply and other — 70%
Transmission (10%)
Distribution (20%)
Generation, supply and other (70%)

Source: Hansard, 22 March 1990

Figure 2: Initial distribution X factors, 1990 (Retail Prices Index plus X, per year)

Eastern Electricity
Eastern Electricity — +0.25
+0.25
East Midlands Electricity
East Midlands Electricity — +1.25
+1.25
London Electricity
London Electricity — +0.00
+0.00
MANWEB
MANWEB — +2.50
+2.50
Midlands Electricity
Midlands Electricity — +1.15
+1.15
Northern Electric
Northern Electric — +1.55
+1.55
NORWEB
NORWEB — +1.40
+1.40
Southern Electric
Southern Electric — +0.65
+0.65
SEEBOARD
SEEBOARD — +0.75
+0.75
South Wales Electricity
South Wales Electricity — +2.50
+2.50
South Western Electricity
South Western Electricity — +2.25
+2.25
Yorkshire Electricity
Yorkshire Electricity — +1.30
+1.30
Weighted average
Weighted average — +1.10
+1.10
+0.0 +0.5 +1.0 +1.5 +2.0 +2.5

Source: Hansard, 22 March 1990

Table 2: Initial distribution X factors announced in March 1990 (Retail Prices Index plus X cap, per year)

Regional Electricity Company X factor (per year)
Eastern Electricity +0.25
East Midlands Electricity +1.25
London Electricity +0.00
MANWEB +2.50
Midlands Electricity +1.15
Northern Electric +1.55
NORWEB +1.40
Southern Electric +0.65
SEEBOARD +0.75
South Wales Electricity +2.50
South Western Electricity +2.25
Yorkshire Electricity +1.30
Weighted average +1.10

Source: Hansard, Electricity Privatisation, 22 March 1990. The five-year range from 0 to +2.5 and the weighted average of about +1.1 are confirmed by the first Director General of Electricity Supply.

Why was competition phased into supply but not distribution?

Competition was introduced progressively in supply, according to customer size. Customers with demand above 1 megawatt, about 30% of the market, were opened to competition in March 1990. The 100 kilowatt to 1 megawatt tier, about 15% of the market, followed in April 1994. The remaining market below 100 kilowatts, about 55%, opened in stages from September 1998 to June 1999.

Figure 3: When supply competition opened, by market share

30%
Above 1 megawatt
Opened March 1990 — 30% of market
15%
100 kilowatts to 1 megawatt
Opened April 1994 — 15% of market
55%
Below 100 kilowatts
Opened Sept 1998 to June 1999 — 55% of market
Above 1 megawatt
March 1990
100 kilowatts to 1 megawatt
April 1994
Below 100 kilowatts
September 1998 to June 1999

Source: DESNZ, Competition in UK electricity markets

Distribution followed a different path. It remained a regulated regional monopoly because it would have been neither practical nor economic to build competing local networks of poles, wires and substations. The Regional Electricity Companies therefore carried both competitive exposure and monopoly protection inside the same corporate group.

This distinction became one of the defining features of the post-privatisation regime. Supply could be opened to entry and customer choice, while distribution had to be disciplined through periodic price controls, efficiency assumptions and limits on the revenue that each regional network could recover. This difference in treatment was one of the main drivers of the later breakdown of the activities into separate supply and distribution companies.

Why did the initial settlement come under pressure?

The initial controls soon looked generous, as the companies reduced costs and earned high profits under caps that allowed real price increases. The 1998 consultation by the electricity regulator recorded that the government’s initial five-year controls typically allowed distribution charges to rise in real terms, and that over that period the Regional Electricity Companies in particular increased profits significantly.

The accounting figures were striking. Distribution operating profit was 34% of turnover in 1990/91 and then ran between 40% and 43% in each year to 1996/97. For low-risk regional monopolies, that profitability level helped justify tougher controls later.

Figure 4: Distribution operation profit as a share of turnover

Regional Electricity Companies, England and Wales

0% 10% 20% 30% 40% 50%
34%
1990/91
Distribution profits: 34%
40 to 43%
1991/92 to 1996/97
Distribution profits: 40%–43%
(range across years)
1990/91
1991/92 to 1996/97 (each year, range shown)

Source: OFFER, 1998 consultation, Table 4 and para 2.15

The regulatory response is the subject of later articles in this series, but it illustrates well how generous the original settlement was. In brief, the regulatory controls in England and Wales were tightened from the mid-1990s. Distribution charges were reduced in real terms by 11% to 17% in 1995/96, by a further 10% to 13% in 1996/97, and then by 3% a year in real terms until March 2000. By 1998, average distribution charges were about 25% lower in real terms than in 1994/95, and average domestic electricity prices about 15% lower.

The initial settlement also set the template that every later review inherited. Control periods ran for a set number of years, five at vesting. Charges were governed by a single RPI plus or minus X formula. The revenue a network could earn was tied to the value of its assets and an allowed return on them, with the starting asset value taken from the flotation price and the original return assumption set at around 6%. Later reviews changed the numbers and sharpened the method, but the shape of the regime, multi-year price caps built on an asset base and a cost of capital, was set here. This is the same regulated cost of capital machinery that MCC Economics analyses in today’s water and energy price reviews.

What does the initial settlement mean for later price controls?

For distribution specifically, the most important pre-review fact is that the electricity distribution monopolies were privatised with price controls already attached. While there was no absence of regulation, the early price controls were deliberately investment-supportive, and in retrospect were too generous. Every review that followed reflected that experience.

The privatisation of electricity distribution was a staged process: the enabling law in 1989, vesting and capital restructuring in early 1990, and flotation of the Regional Electricity Companies in December 1990. This was underpinned by an initial RPI plus X price control, and was followed by the promotion of competition in the supply business, phased by customer size, and tougher regulatory reviews for the distribution businesses.

How did Scotland and Northern Ireland differ?

Scotland and Northern Ireland followed different paths from England and Wales. Scottish Power and Scottish Hydro-Electric stayed vertically integrated, generating and distributing electricity, with the Scottish nuclear assets vested in Scottish Nuclear. The first two companies were sold in June 1991 through a fixed-price offer for all of each company at 240 pence per share, combined with a back-end tender, while the latter was kept under government ownership. The offer was about three times subscribed and  net proceeds were 3.5 billion pounds.

Northern Ireland followed a different legal and commercial route. Its industry was smaller, isolated from the rest of the United Kingdom and from the Republic of Ireland, heavily reliant on oil-fired plant, and without an immediate prospect of a competitive market. Its restructuring used the Electricity (Northern Ireland) Order 1992. The power stations raised 708 million pounds and Northern Ireland Electricity raised 362 million pounds when sold in June 1993.

References

  1. Department for Business, Energy and Industrial Strategy. (2022). Competition in UK electricity markets [Energy Trends special feature article]. https://assets.publishing.service.gov.uk/media/6334353ee90e0772dc96514f/Competition_in_UK_Electricity_Markets.pdf
    Phasing of retail competition: above 1 megawatt, 100 kilowatt to 1 megawatt, and below 100 kilowatts.
  2. Electricity Act 1989, c. 29 (UK). https://www.legislation.gov.uk/ukpga/1989/29/contents/enacted
    Long title and structure of the Act: regulator, consumer committees, licensing, vesting and dissolution of the Electricity Boards and Electricity Council.
  3. Hansard. (1990, March 22). Electricity privatisation (House of Commons Debates, Vol. 169, cols. 691W–692W). https://api.parliament.uk/historic-hansard/written-answers/1990/mar/22/electricity-privatisation
    Initial transmission and distribution controls, the Retail Prices Index plus X factors, the weighted average X, final-price shares and the investment allowance.
  4. Hansard. (1991, January 28). Electricity privatisation (House of Commons Debates, Vol. 184, cols. 637–638). https://api.parliament.uk/historic-hansard/commons/1991/jan/28/electricity-privatisation
    Government statement that the sale would return close to 8 billion pounds, with over 5 billion from shares and almost 3 billion from debt.
  5. Office of Electricity Regulation. (1998). Reviews of public electricity suppliers 1998 to 2000: Price controls and competition. A consultation paper. https://www.ofgem.gov.uk/sites/default/files/docs/1998/07/price-controls-and-competition-a-consultation-paper.pdf
    Background on the initial controls, profitability, and the real-price reductions to 1998. The Office of Electricity Regulation later merged with the gas regulator to form Ofgem.
  6. Rhodes, C., Hough, D., & Butcher, L. (2014). Privatisation (Research Paper No. 14/61). House of Commons Library. https://researchbriefings.files.parliament.uk/documents/RP14-61/RP14-61.pdf
    Electricity Supply Industry annex: restructuring, the sale, proceeds, Scotland and Northern Ireland.

Authors

 What’s next

Are Stock Returns Predictable? Rewarding Patient Investors & Powerful Binding Equilibriums

Delve into stock market predictability with Tobin's Q and dividend yield, challenging conventional views.

Heading 1

Heading 2

Heading 3

Heading 4

Heading 5
Heading 6

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur.

Block quote

Ordered list

  1. Item 1
  2. Item 2
  3. Item 3

Unordered list

  • Item A
  • Item B
  • Item C

Text link

Bold text

Emphasis

Superscript

Subscript

Featured

This paper has been published on following other platforms

No items found.

I was delighted that MCC's work was completed on time, and within budget, helping us deliver important changes and improvements, to the benefit of our stakeholders. ​ MCC's report is published on the CCC website.

- Bea Natzler
Team Leader at Climate Change Committee, UK

I am delighted to recommend MCC Economics. Specifically, I worked closely with PJ, who helped us with our Nuclear and CCUS projects. PJ helped us develop new policies and answer questions from our stakeholders. ​​His support helped us deliver important changes and improvements, to the benefit of our stakeholders.

- Gordon Hutcheson
Head of Nuclear Policy at Ofgem, UK

MCC Economics has helped us better understand the most important issues for our stakeholders, including: charges, shareholder returns, debt payments and inflation impacts.

- Leila N. Nasr
Section Head at Department of Energy, Abu Dhabi

I am delighted to recommend PJ and his team at MCC Economics. We've been working together on National Policy Statements to help meet net zero targets for 2030 and 2050. We initially appointed MCC Economics to support us on offshore wind consultation analysis and have recently reappointed MCC Economics to undertake a larger consultation analysis role across all sectors, including hydrogen, CCUS and networks. I can confirm that PJ and his team have shown excellent spreadsheet skills, alongside very good project management, planning and analysis skills, helping us deliver important changes, and continuous improvements, to the benefit of our stakeholders.

- Amy McHugh
Head of Environment in the Energy Infrastructure Planning Policy, UK

I am delighted to recommend PJ and his team from MCC Economics. They helped us with our price controls for Heathrow airport and for NATS (En Route) plc (the air traffic services provider). Specifically, the MCC team helped us deliver important changes and improvements to our financial models and supporting policy documents, to the benefit of our stakeholders.

- Dan Rock
Head of Corporate Finance at CAA, UK

I am delighted to confirm that I worked with PJ on a retail project in 2015. The project helped stakeholders understand electricity costs and charges. Specifically, the project helped us explain to stakeholders, internally and externally, why electricity charges differed across the regions (GB, NI & Ireland). PJ was a key member on the project team, which helped deliver changes and improvements in the understanding of energy retail.

- Kevin Shiels
Director at Utility Regulator, Northern Ireland