Maximising Grid Capacity for High-Renewable Power Systems

Quick Answer

Grids with high shares of renewables gain capacity fastest by building new wires and using flexibility at the same time. New lines take years: Britain’s Eastern Green Links arrive between 2029 and 2035, and Australian transmission cost estimates now run up to around 100% higher than in the 2024 plan.

Grid flexibility is filling the gap. Britain’s Demand Flexibility Service enrolled 1.6 million households and businesses, and average battery output in Australia’s main grid more than tripled in a year to 359 MW. Regulators are clearing the way, with Ofgem approving a connection queue that puts ready projects first.

‍

About

Grids with high shares of renewable energy add usable capacity fastest when transmission investment, demand response, battery storage and regulation move together. This paper compares Britain, Abu Dhabi and Australia and finds that new lines are arriving slowly and at rising cost, so flexible demand, batteries and reformed grid connection queues are now doing much of the work.

‍

Key takeaways

‍

1 | Which transmission upgrades are adding grid capacity for renewables?

All three regions are building new links and substations to move renewable power from where it is generated to where it is used, but on very different timetables.

Britain's Eastern Green Links each carry up to 2 GW from Scotland to England. According to National Grid, Links 1 and 2 are due in 2029, Links 3 and 4 from 2033, and Link 5 in 2035.

Financing is following. The National Wealth Fund lent ScottishPower £600m for seven priority network projects in May 2025, and a further £600m for Eastern Green Link 4 in March 2026.

Abu Dhabi is reinforcing its 400 kV network. TAQA Transmission awarded the ICAD-4 substation to Linxon in February 2025, for commissioning in 2028, and will connect the new round-the-clock solar and storage project.

Australia faces the steepest cost pressure. The Victoria to New South Wales Interconnector West (VNI West) should unlock about 3.4 GW of new renewables, but its Victorian section has moved to November 2030, and the Australian Energy Market Operator (AEMO) put the rise in real cost estimates for new overhead lines at 25% to 55% in its May 2025 draft, before its final report of August 2025 dropped the split between lines and substations and said estimates run up to around 100% higher in some cases (Table 1 and Figure 1). 

‍

‍

Table 1: Grid upgrades in Great Britain, Abu Dhabi and Australia, status at September 2026

‍

RegionProjectKey factsLatest status
Great BritainEastern Green Link 32 GW, 525 kV high-voltage direct current link of about 680 km from Aberdeenshire to Norfolk, developed by SSEN Transmission and National Grid Electricity TransmissionCable contract signed with NKT in March 2026; construction due to start in 2029, with operation targeted for 2033
Eastern Green Link 42 GW subsea link of 530 km between Fife and Norfolk, developed by SP Energy Networks and National Grid£600m of National Wealth Fund financing, March 2026; operation expected from 2033
Eastern Green Link 52 GW, 525 kV link from Aberdeenshire to Lincolnshire, with a proposed 585 km subsea cable landing at Anderby CreekConsultation on the English section ran to 24 July 2026; energisation targeted for 2035
National Wealth Fund loan£600m to ScottishPower in May 2025 for seven priority network projectsFollowed by the separate £600m for Eastern Green Link 4
Abu DhabiICAD-4 substation400/220 kV substation in the Industrial City of Abu Dhabi; turnkey contract awarded by TAQA Transmission to Linxon in February 2025Commissioning planned for 2028, to serve growing load and the retirement of the Sas Al Nakheel plant
Masdar and EWEC round-the-clock project5.2 GW of solar with 19 GWh of batteries, designed to deliver 1 GW continuouslyConstruction started October 2025; operation expected in 2027
EWEC, TAQA and Masdar infrastructure programmeAbout AED 36bn, with a quarter for grid assets on the regulated asset base; TAQA Transmission to connect new generation, including the round-the-clock projectAnnounced April 2025
AustraliaVNI West500 kV double-circuit line linking the Murray River and Western Victoria renewable energy zones with New South Wales; expected to unlock about 3.4 GW of new renewables and add about 1.9 GW of transfer capacityVictorian completion moved to November 2030; decision on New South Wales approval expected late 2026
Waratah Super Battery850 MW / 1,680 MWh, with at least 700 MW / 1,400 MWh contracted as a network protection schemeFirst 350 MW online August 2025; transformer failure October 2025; replacement energised September 2026, final testing under way
Transmission Acceleration Facility, New South WalesAU$2.1bn over four years in the 2025‑26 state Budget for five renewable energy zonesBuilds on AU$1.1bn already invested

Ten projects and funding decisions cited in the paper, with their latest published status. Each Eastern Green Link is rated at 2 GW.

Sources: SSEN Transmission, Eastern Green Link 3 and Eastern Green Link 5; National Grid, Eastern Green Link 3 contracts and programme dates; Electrical Review, Eastern Green Link 5 consultation, June 2026; Enerdata, NKT contract for Eastern Green Link 3, March 2026; National Wealth Fund, ScottishPower financing for Eastern Green Link 4, March 2026; Saudi Gulf Projects, Linxon awarded 400 kV substation, February 2025; Linxon, ICAD-4 press release; Masdar, round-the-clock project; ESS News, construction start, October 2025; TAQA Transmission, EWEC, TAQA and Masdar programme, April 2025; Transgrid, VNI West; pv magazine Australia, VNI West preferred option; Victorian Planning, VNI West referral; EnergyCo, Waratah Super Battery; Akaysha Energy, Waratah update; Tech Times, replacement transformer energised, September 2026; NSW Government, 2025-26 Budget Papers.

‍

Why it matters. Every link in the British programme is rated at 2 GW, so Eastern Green Links 3 and 4 together add about 4 GW of north to south capacity, not the 15 GW stated in the original paper.

The dates matter as much as the ratings. Eastern Green Links 3 and 4 are not due to operate until 2033, Link 5 until 2035, and VNI West has slipped to 2030, while Waratah went from announcement in early 2022 to its first 350 MW in August 2025. That gap is the case for building storage alongside wires, although Waratah's transformer failure shows that faster assets carry delivery risk too.

‍

AEMO's own summary of the cost update is blunt:

‍

Transmission costs have risen, particularly for overhead lines

Australian Energy Market Operator (AEMO), Draft 2025 Electricity Network Options Report, May 2025, p. 5, executive summary heading.

‍

‍

Figure 1: How AEMO's transmission cost estimates changed between its draft and final 2025 reports

Increase in real cost estimates against the 2024 Integrated System Plan. The May 2025 draft gave separate ranges for overhead lines and substations. The final report of August 2025 no longer splits them and publishes only an upper figure, so its bar has no lower bound.

‍

Draft, May 2025: overhead lines 25% to 55% higher; substations 10% to 35% higher. Final, August 2025: all transmission estimates up to around 100% higher in some cases.

Increase in real cost estimates against the 2024 Integrated System Plan. The May 2025 draft gave separate ranges for overhead lines and substations. The final report of August 2025 no longer splits them and publishes only an upper figure, so its bar has no lower bound.

Sources: Australian Energy Market Operator (AEMO), Draft 2025 Electricity Network Options Report, May 2025, p. 5, executive summary; AEMO, 2025 Electricity Network Options Report, August 2025, executive summary, page not verified; AEMO, news update on the draft report.

‍

Why it matters. AEMO's numbers moved during its own consultation. In May 2025 it put the increase at 25% to 55% for overhead lines and 10% to 35% for substations. By August it had dropped the split and said estimates run up to around 100% higher in some cases, citing supply chain pressure, scope revision, competition between concurrent projects, project complexity, social licence and contracting costs.

That shifts the arithmetic of the whole plan. The final 2026 Integrated System Plan, published in June 2026, carried higher costs for transmission and wind and lower costs for solar and batteries than its predecessor. When wires get dearer and batteries cheaper, assets that let existing lines carry more power, such as Waratah, move up the order of merit.

2 | How is demand response freeing up grid capacity?

Demand response, which pays customers to use less power at peak times, now works at scale in all three regions, from British households to Abu Dhabi industry and Western Australia's contracted reserves.

In Britain, according to the system operator's review, 1.6 million households and businesses took part in the Demand Flexibility Service in winter 2022/23, cutting demand by about 3,300 MWh over 22 events (Table 2).

In 2023/24, third-party apps paid participants between about £2.40 and £3.00 per kWh saved (Table 3).

‍

‍

Table 2: Great Britain's Demand Flexibility Service, winter 2022/23

‍

MeasureResult
Households and businesses taking part1.6 million
Providers (suppliers and aggregators)31
Events22: 20 one-hour tests and 2 live events, on 23 and 24 January 2023
Total demand reductionAbout 3,300 MWh
Payments by the system operatorAbout £11.1m (£8.0m for tests, £3.1m for live events)
Average reduction per event (MCC calculation)About 150 MWh
Average payment per kWh reduced (MCC calculation)About £3.36

Headline results from the system operator's review of the first winter. The last two rows are derived from the figures above them.

Source: National Grid Electricity System Operator (now NESO), Demand Flexibility Service winter 2022/23 review, August 2023; NESO, results announcement.

‍

Why it matters. The service reached people at a scale Britain had not seen before, but the energy it moved was small: about 150 MWh per event, and most events lasted an hour. That points to reductions in the low hundreds of megawatts, not the 1 to 2 GW shift quoted in the paper's incentives table.

At about £3.36 per kWh it was also expensive energy. Its value lay in proving that households would respond at short notice, which later versions built on by running events all year and, from April 2026, paying households to use more power when supply is plentiful.

‍

‍

Table 3: Rewards offered by third-party apps under the Demand Flexibility Service, winter 2023/24

‍

AppReward per kWh savedShare of system operator payment passed onHow it was paid
LoopAbout £2.50About 80%Gift cards at the end of the scheme
HugoAbout £2.40At least 80%PayPal at the end of the scheme
EquiwattAbout £2.70About 90%Gift cards at the end of the scheme
IviePrize draw entriesAbout 85% (value of prizes)Weekly £25 vouchers, up to a £1,000 cash prize
Uswitch (uTrack)£3.00100%One-off payment, plus a bonus for first-time users

Rewards for the 2023/24 scheme as compiled by Sunsave. This table replaces the screenshot in the original paper.

Sources: Sunsave, The Demand Flexibility Service explained; Loop reward also reported by Which?, rewards for using less electricity at peak times.

‍

Why it matters. Uswitch passed on the whole payment at £3 per kWh, so the table shows roughly what the system operator was paying providers that winter; the other apps kept 10% to 20% for themselves.

The rewards were real but brief. Money Saving Expert's guide, updated in January 2026, now tells readers to expect only a few pounds per event, so these rates describe a scheme that has since changed, not what households can earn today.

‍

In Abu Dhabi, the second phase of the Department of Energy's demand response pilot started in May 2025. It targets more than 250 MW from over 30 industrial and commercial organisations, with Energy Pool as aggregator, and supports a policy target of 200 MW under contract by 2030.

Western Australia shows how quickly peaks are rising. Its demand record, unchanged since 2016, has been broken repeatedly since late 2023, beginning with 4,233 MW in February 2024, and the six highest peaks all fell within twelve months (Figure 2).

‍

‍

Figure 2: Western Australia's six highest operational demand peaks, February 2024 to January 2025

Megawatts, highest 5-minute interval, South West Interconnected System. Numbers below each marker give its rank. Filled markers match figures AEMO has published. Hollow markers are values from AEMO's record demand slide, reproduced in the original paper; published data on a different basis differs from them by 8 MW or less.

‍

Highest operational demand peaks, in date order: 1 February 2024, 4,169 MW (5th); 18 February 2024, 4,233 MW (2nd); 19 February 2024, 4,170 MW (4th); 20 February 2024, 4,193 MW (3rd); 11 December 2024, 4,163 MW (6th); 20 January 2025, 4,486 MW (record). Record set in 2016: 4,006 MW.

Megawatts, highest 5-minute interval, South West Interconnected System. Numbers below each marker give its rank. Filled markers match figures AEMO has published. Hollow markers are values from AEMO's record demand slide, reproduced in the original paper; published data on a different basis differs from them by 8 MW or less.

Sources: AEMO, Quarterly Energy Dynamics Q1 2024, pp. 64 to 65; AEMO, Quarterly Energy Dynamics Q4 2024; AEMO, Quarterly Energy Dynamics Q1 2025, p. 5; AEMO, 2024 Wholesale Electricity Market Electricity Statement of Opportunities, section 2.3.1, for the 2016 record; AEMO, 2024 WEM ESOO Data Register, Figure 14 data; AEMO, 2026 WEM Electricity Statement of Opportunities, pp. 39 to 40, for the 2025-26 peak and the 2026-27 forecast; Ampere Labs, Q1 2024 WEM Review. Values for 1, 19 and 20 February 2024 as shown in AEMO's record demand slide.

‍

Why it matters. Western Australia's demand record stood at 4,006 MW from 2016 until late 2023. Since then it has been broken repeatedly, and all six of the highest peaks shown by AEMO fell within twelve months. The record now stands 480 MW higher, at 4,486 MW.

Every one of these peaks came in the early evening, after rooftop solar had faded. The 2025-26 summer was mild and peaked at 4,219 MW, so the record still stands, but AEMO's one-in-ten-year forecast for 2026-27 is 4,709 MW. That evening peak is what batteries, demand response and firm capacity now have to cover.

‍

AEMO activated 126 MW of demand reductions when operational demand reached a record 4,486 MW on 20 January 2025 (Figure 3). Its planning report also flags a gap in how the market's standing demand programmes are contracted:

‍

Demand Side Programmes (DSP) could also play an increasingly important role in meeting this demand; however, under current rules they are not obligated to be available after 8:00 pm. Amending Rules have been drafted to address this issue in the future.

AEMO, on demand side programmes in Western Australia, 2025 Wholesale Electricity Market Electricity Statement of Opportunities, June 2025, p. 5, executive summary.

‍

‍

Figure 3: Demand reductions activated at Western Australia's record peak on 20 January 2025, against the forecast capacity surplus for summer 2025-26

Megawatts. AEMO activated 126 MW of demand reductions at the record 4,486 MW peak; without them, it estimates peak demand would have reached 4,594 MW. The surplus is capacity above AEMO's requirement, which already includes a reserve margin.

‍

Activated on 20 January 2025: 94.5 MW essential system services, 20 MW demand side programmes, 11.5 MW supplementary capacity (126 MW in total). Forecast surplus for summer 2025-26: 5 MW.

Megawatts. AEMO activated 126 MW of demand reductions at the record 4,486 MW peak; without them, it estimates peak demand would have reached 4,594 MW. The surplus is capacity above AEMO's requirement, which already includes a reserve margin.

Sources: AEMO, 2025 Wholesale Electricity Market Electricity Statement of Opportunities, June 2025, pp. 9, 12 and 38; AEMO, Quarterly Energy Dynamics Q1 2025, p. 5.

‍

Why it matters. The demand reductions activated at this single peak were 25 times larger than the capacity surplus AEMO forecast for the following summer: 126 MW, against 5 MW over and above its required reserve margin.

The mix matters too. Three quarters came from essential system service contracts rather than the market's standing demand programmes, and AEMO notes those programmes are not obliged to be available after 8 pm, even though peaks now run later into the evening. AEMO presents the response as protecting supply, not as displacing gas, which still met more than half of demand at the peak.

‍

‍

These programmes flatten peaks, free transformer headroom and give operators rapid, software-based "virtual lines". The rules that support them include:

‍

  • building regulations that raise efficiency standards;
  • utility regulations that curb vested interests;
  • dynamic tariffs and price signals;
  • mandatory and improved metering;
  • innovation funding;
  • demand aggregation rules;
  • open data;
  • distributed energy resource management systems; and
  • smart grid orchestration, including automated demand control.

‍

3 | How do customer incentives and demand-side management affect grid stability?

They stabilise the grid most when demand response is bought as a fast, clearly defined service, rather than paid only for energy delivered at scarce moments.

In Australia, 12 registered demand response providers supplied 19% of contingency raise frequency reserves in Q1 2025, an average of 330 MW.

In the same quarter, the wholesale demand response mechanism dispatched only 4 MWh, down from 87 MWh a year earlier (Figure 4).

Abu Dhabi and Britain rely on events called at peak times, paid through an aggregator or through suppliers and apps (Table 4).

‍

‍

Table 4: How demand response is procured and what it delivers

SchemeWho takes partHow it worksScale and results
Demand Flexibility Service, Great BritainHouseholds and small businessesPaid per kWh of verified reduction during called events, through suppliers and apps1.6 million participants and about 3,300 MWh over winter 2022/23 (Table 2)
Demand response pilot, phase 2, Abu DhabiLarge industrial and commercial usersReductions at peak times coordinated by Energy Pool, the emirate's first demand response aggregator, over a 12-month pilotLaunched May 2025; targets more than 250 MW from over 30 organisations; policy target of 200 MW under contract by 2030
Frequency control ancillary services, Australia12 registered participantsPaid for being enabled to cut load quickly when frequency falls19% of contingency raise enablement in Q1 2025, averaging 330 MW
Wholesale demand response mechanism, Australia20 registered unitsPaid for scheduled reductions in the energy market4 MWh dispatched in Q1 2025, down from 87 MWh a year earlier (Figure 4)

Four schemes cited in the paper, compared by participant type, payment basis and published results. This table replaces the original incentives table, whose £5.50 per kWh figure is no longer supported by its source.

Sources: NESO (Table 2); Abu Dhabi Department of Energy, second phase of the demand response pilot, May 2025; Zawya, demand response aggregator progress, September 2025; AEMO, Quarterly Energy Dynamics Q1 2025, pp. 39 to 40.

‍

Why it matters. The same flexible load performs very differently depending on the product it is sold into. In Australia, demand response supplied almost a fifth of contingency frequency reserves in early 2025 while barely registering in the energy market mechanism.

The Australian results suggest that short, clearly defined services that pay for being available draw in flexible load more readily than schemes that pay only for energy delivered at scarce moments. That is a design lesson for Abu Dhabi as its pilot moves towards a permanent programme, and it qualifies the paper's view that Australia's rule changes put flexible load on an equal footing.

‍

AEMO says the dispatch figure understates what is out there:

‍

This market does not capture the full extent of price-responsive resources that currently exist in the NEM, however, making it difficult to predict and report on their operation.

AEMO, on the wholesale demand response mechanism, Quarterly Energy Dynamics Q1 2025, May 2025, p. 39. NEM: National Electricity Market.

‍

‍

Figure 4: Wholesale demand response dispatched in Australia's National Electricity Market, by quarter

‍

Megawatt hours per quarter: Q4 2023, 1; Q1 2024, 87; Q2 2024, 109; Q3 2024, 182; Q4 2024, 103; Q1 2025, 4.

Megawatt hours per quarter, Q4 2023 to Q1 2025. Dispatch fell to 4 MWh in Q1 2025, spread across two days.

Source: AEMO, Quarterly Energy Dynamics Q1 2025, Figure 61, p. 39.

‍

Why it matters. Even in its best quarter the mechanism dispatched 182 MWh, about as much as one average Demand Flexibility Service event in Britain (Table 2).

AEMO links the fall in early 2025 to calmer wholesale prices, and says the mechanism captures only part of the price-responsive load that already exists. A rule change made in December 2024 requires AEMO to report each year on unscheduled price-responsive resources, starting in 2026, which should make the rest visible. AEMO paused and reset the wider implementation in April 2026, and proposed rule changes would defer the dispatch and incentive parts by up to two and a half years.

4 | Which battery energy storage projects matter most for the grid?

Three battery projects stand out, each doing a different job: stabilising the grid in Scotland, supplying solar power around the clock in Abu Dhabi, and letting existing lines carry more power in New South Wales.

‍

  • Blackhillock, Scotland: 200 MW / 400 MWh, operating since 3 March 2025 and the first project delivered under the system operator's Stability Pathfinder.
  • Masdar and Emirates Water and Electricity Company (EWEC) round-the-clock project, Abu Dhabi: 5.2 GW of solar and 19 GWh of batteries to supply 1 GW continuously, under construction since October 2025.
  • Waratah Super Battery, New South Wales: 850 MW / 1,680 MWh, acting as a "shock absorber" so that existing lines serving Sydney, Newcastle and Wollongong can carry more power.

‍

Britain's system operator ties the project to its zero-carbon operation target:

‍

Our 2025 ambition to enable zero carbon operation of Great Britain's national electricity network is central to NESO's mission. The delivery by Zenobe of this grid forming battery is a major accomplishment and brings us a step closer to this goal.

Fintan Slye, Chief Executive, National Energy System Operator (NESO), on Blackhillock, Zenobē, 2025.

‍

Masdar presents its project as an answer to the oldest limitation of renewables:

‍

For decades, the biggest barrier facing renewable energy has been intermittency, to be able to source uninterrupted clean power day and night. This has been the moonshot challenge of our time, and now, thanks to the resolute support of President His Highness Sheikh Mohamed bin Zayed Al Nahyan, with this groundbreaking project we have found the solution.

Dr Sultan Al Jaber, Chairman of Masdar, launching the round-the-clock project, Masdar newsroom, January 2025.

‍

‍

Table 5: Four projects behind the paper's storage milestones

‍

ProjectDeveloperSizeRole on the gridStatus
Blackhillock, ScotlandZenobē200 MW / 400 MWh in phase 1; a further 100 MW planned for 2026Grid-forming battery providing stability services, including short-circuit level and inertia, under the system operator's Stability PathfinderOperating since 3 March 2025
Round-the-clock project, Abu DhabiMasdar and EWEC5.2 GW of solar and 19 GWh of batteriesFirm output of 1 GW around the clock; about 5.7 million tonnes of carbon dioxide avoided a yearUnder construction since October 2025; operation expected in 2027
Al Ajban solar, Abu DhabiMasdar (60%), EDF Renewables and Korea Western Power (20% each)1.5 GW (AC) of solar; no batteryDaytime solar supply for about 160,000 homes; more than 2.4 million tonnes of carbon dioxide avoided a yearAwarded April 2024; construction contract awarded to PowerChina Huadong, July 2024; first panel installed February 2026; commercial operation scheduled for Q3 2026
Waratah Super Battery, New South WalesAkaysha Energy for EnergyCo850 MW / 1,680 MWhProtection scheme that lets existing lines carry more power, with spare capacity traded in the marketFinal commissioning under way, September 2026

The original paper merged the round-the-clock project and Al Ajban into one scheme. They are separate projects with different developers.

Sources: Wärtsilä, Blackhillock now operational, March 2025; Zenobē, Blackhillock launch; Masdar, round-the-clock project; ESS News, construction start, October 2025; Masdar, Al Ajban award, April 2024; Masdar, Al Ajban financial close; Zawya, construction contract and first panel, February 2026; EnergyCo, Waratah Super Battery; Tech Times, Waratah transformer update, September 2026.

‍

Why it matters. The word storage covers three different jobs here. Blackhillock sells stability, the Masdar and EWEC scheme sells firm energy, and Waratah sells network capacity. Each needs its own contract and regulatory treatment, so the harder question for regulators is not whether to buy storage but which service they are buying.

The system operator describes Blackhillock as the first grid-forming battery on Britain's network. The sources for Waratah describe a protection scheme, so the paper's grid-forming label for Waratah needs a source or should go.

‍

Storage soaks up surplus solar, defers line upgrades and supplies fast frequency response, which makes it central to 100% renewable ambitions.

‍

5 | How is machine learning improving solar forecasting and reserve setting?

Machine learning is making solar forecasts more accurate and reserve levels leaner, which lowers balancing costs without new infrastructure.

Britain's system operator, now the National Energy System Operator (NESO), made its day-ahead solar forecasts 33% more accurate in 2019, working with the Alan Turing Institute.

Its Dynamic Reserve Setting tool, built with the Smith Institute, sets reserve levels a day ahead. NESO reports that the tool has cut how much reserve it needs to buy: 

‍

Why it matters. The word storage covers three different jobs here. Blackhillock sells stability, the Masdar and EWEC scheme sells firm energy, and Waratah sells network capacity. Each needs its own contract and regulatory treatment, so the harder question for regulators is not whether to buy storage but which service they are buying.

The labels matter as well. The system operator describes Blackhillock as the first grid-forming battery on Britain's network, a service that holds the system steady. The original paper gave Waratah the same label, but its published sources describe a protection scheme that frees up capacity on existing lines, which is a different job.

‍

National Grid Electricity Distribution's 2024 scenarios were the first by a distribution system operator to model maritime, aviation, rail and agriculture demand.

In Australia, AEMO published its final 2025 inputs and scenarios in July 2025, reviewed by the Australian Energy Regulator in August, and its 2026 Integrated System Plan in June 2026 (Figure 5).

‍

‍

Table 6: Forecasting and planning tools for variable solar

‍

RegionToolWhat it has deliveredWhy it matters for the grid
Great BritainMachine learning solar forecast, built by the system operator with the Alan Turing InstituteDay-ahead solar forecasts 33% more accurate (2019); the system operator has since worked with Open Climate Fix on short-term forecastsLets the control room balance the system at lower cost
Dynamic Reserve Setting, built by the system operator with the Smith InstituteMachine learning sets reserve levels a day ahead; initial results show on average 300 MW less reserve per half-hour periodLowers balancing costs and emissions
Distribution Future Energy Scenarios 2024, published January 2025National Grid Electricity Distribution became the first distribution system operator to model maritime, aviation, rail and agriculture demandHelps time substation and network upgrades
Australia2025 Inputs, Assumptions and Scenarios Report and Electricity Network Options ReportFinal inputs report published 31 July 2025; final network options report published August 2025; addendum to the inputs report in December 2025Inputs to the 2026 Integrated System Plan, published in June 2026 (Figure 5)

Corrected from the original table: the 33% gain applies to day-ahead forecasts, not hour-ahead, and the scenarios described are the 2024 edition.

Sources: Alan Turing Institute, Towards a greener grid; NESO, work with Open Climate Fix; NESO, Dynamic Reserve Setting; National Grid Electricity Distribution, Future Energy Scenarios will guide network development, January 2025; AEMO, 2025 Electricity Network Options Report, August 2025; AEMO, 2026 Integrated System Plan.

‍

Why it matters. Forecasting gains pay off only if planning can absorb them. Britain's 33% improvement dates from 2019, and the Australian cycle in Figure 5 shows how long new inputs take to reach an investment plan.

The original paper claimed AI forecasting cuts reserve requirements by double-digit percentages, a figure with no published source behind it. The measured result is narrower: in early testing the system operator's tool needed on average 300 MW less reserve per half-hour period.

‍

‍

Figure 5: Australia's 2026 Integrated System Plan cycle, December 2024 to June 2026

‍

Confirmed in AEMO and regulator publicationsDate from AEMO’s consultation timeline slide
  1. 11 December 2024Draft 2025 Inputs, Assumptions and Scenarios Report, stage 1, published
  2. 23 January 2025Stage 1 public webinar
  3. 11 February 2025Stage 1 written and verbal submissions close
  4. 28 February 2025Draft inputs report, stage 2, published
  5. March 2025Stage 2 webinar held and submissions close
  6. May 2025Draft 2025 Electricity Network Options Report published, with higher transmission cost estimates (Figure 1)
  7. 23 June 2025Submissions on the draft network options report close
  8. 31 July 2025Final 2025 Inputs, Assumptions and Scenarios Report published
  9. August 2025Final 2025 Electricity Network Options Report published, dropping the separate cost ranges and citing increases of up to around 100%
  10. 28 August 2025Australian Energy Regulator publishes its transparency review and asks AEMO to explain some inputs further
  11. 10 December 2025Draft 2026 Integrated System Plan published, with an addendum to the inputs report
  12. 25 June 2026Final 2026 Integrated System Plan published

Key milestones from the first draft inputs in December 2024 to the final plan in June 2026. Hollow markers show dates from AEMO's consultation timeline slide, reproduced in the original paper.

Sources: AEMO, Draft 2025 Electricity Network Options Report, p. 11, for the draft inputs report dates; AEMO, draft network options report; AEMO, final 2025 Electricity Network Options Report, August 2025; AEMO, 2026 Integrated System Plan; Australian Energy Regulator, transparency review of the 2025 inputs report; WattClarity, AEMO releases the 2026 plan, June 2026. Dates for the January to March 2025 webinars and submissions as shown in AEMO's consultation timeline slide for the draft 2025 inputs report.

‍

Why it matters. The cycle took eighteen months from the first draft inputs to the final plan. Even after the inputs were finalised in July 2025, AEMO had to issue an addendum following the regulator's review. The cost rises in Figure 1 were fixed in mid-2025 for a plan that runs to 2050.

Because the plan is revised only every two years, inputs date quickly. That is the practical case for the paper's call for joint scenario planning between system operators and network companies.

6 | How are system operators and governments reforming grid connections and planning?

They are redesigning grid connection queues and planning processes, so that network companies, operators and governments stop duplicating each other's work.

‍

‍

NESO explained why the queue had to pause:

‍

Grid connections applications have continued to grow over the last year to the point that it is no longer possible to deliver connections reforms in parallel with the existing connections process. In 2023/24 alone, NESO received over 1,700 applications to connect to the national electricity transmission system, leaving more projects already in the queue than are required for the energy system in 2030 or even 2050.

NESO, Next steps in grid connections reform, January 2025.

‍

The New South Wales review set out a similar aim for planning:

‍

In particular, the review is to consider options to reduce duplication and ensure coordination between entities involved in transmission planning in NSW.

Independent review panel, on the review's terms of reference, NSW transmission planning review: Interim Report, 27 June 2025, p. 4, executive summary.

‍

‍

7 | How can grids meet peak and minimum demand while staying resilient?

They need to plan for both ends of the day: record-low midday demand as rooftop solar grows, and evening peaks increasingly met by storage.

In Britain, NESO warned in April 2025 that national demand could fall below its 13.4 GW record:

‍

As solar and other generation on the regional distribution networks increases, the requirement for electricity to flow across the national network reduces. Potentially Britain will see its lowest national demands ever, including compared to 2020 COVID-19 Pandemic Lockdown demand.

NESO, 2025 Summer Outlook announcement, April 2025.

‍

A new record of 12.8 GW has since been set, and NESO's 2026 Summer Outlook puts the chance of a lower figure this summer at about 75%.

In Dubai, the 250 MW / 1,500 MWh Hatta pumped-storage plant provides six hours of storage at full output.

In Australia's National Electricity Market, average battery output rose from 98 MW in Q1 2025 to 359 MW in Q1 2026, after 4,445 MW of new battery capacity connected (Figure 6).

‍

‍

Table 7: Planning signals for 2030 and beyond

‍

RegionSignalLatest data
Great BritainRecord-low national demand as rooftop solar growsNESO's 2025 Summer Outlook warned demand could fall below the 13.4 GW record set in June 2020. A new record of 12.8 GW has since been set, and the 2026 Outlook puts the chance of a lower figure this summer at about 75%
United Arab Emirates (Dubai)Pumped storage at Hatta, built by the Dubai Electricity and Water Authority250 MW / 1,500 MWh; the authority targeted full completion by the end of Q2 2025
AustraliaRapid growth in grid-scale batteriesBattery availability rose 46% to 1,193 MW in Q1 2025, and average output rose 86% to 98 MW. By Q1 2026 average discharge was 359 MW, after 4,445 MW / 11,219 MWh of new capacity (Figure 6)

Updated from the original table, which placed the Hatta scheme in Abu Dhabi.

Sources: NESO, 2025 Summer Outlook announcement, April 2025; NESO, Summer Outlook 2026; Dubai Electricity and Water Authority, Hatta progress update, November 2024; AEMO, Quarterly Energy Dynamics Q1 2025, p. 38; AEMO, Quarterly Energy Dynamics Q1 2026, p. 3.

‍

Why it matters. All three signals point the same way. The hard hours are no longer only the evening peak but also the sunny, low-demand middle of the day, and storage is the tool that helps at both ends.

Britain now plans for demand falls once seen only during the 2020 lockdown. Hatta's 1,500 MWh gives six hours of storage at full output, the kind of duration needed to move Gulf solar into the evening. Australia's battery fleet shows how quickly such capacity can be added: more than 4,400 MW in a single year.

‍

‍

Figure 6: Average battery discharge in Australia's National Electricity Market, first quarters of 2024 to 2026

‍

Average battery discharge: about 53 MW in Q1 2024, 98 MW in Q1 2025, 359 MW in Q1 2026.

Megawatts, averaged across all hours. The Q1 2024 value is derived from AEMO's reported increase of 45 MW to Q1 2025.

Sources: AEMO, Quarterly Energy Dynamics Q1 2025, p. 38; AEMO, Quarterly Energy Dynamics Q1 2026, p. 3.

‍

Why it matters. Output has grown almost sevenfold in two years, yet averaged across all hours it is still small next to a fleet with 1,193 MW available in Q1 2025, because batteries earn their money in a few hours of each day.

What is changing is where they earn it. In Q1 2025 battery revenue from frequency services fell 72% as more batteries competed for it, while energy trading revenue rose 44%. Storage is moving from a niche reserve product into the core energy market, which is why it is no longer optional.

8 | Does separating transmission from distribution help or hinder Gulf grids?

In Abu Dhabi it has mostly helped, because transmission and distribution sit in separate companies under one owner.

TAQA Transmission owns the high-voltage grid, including the 400 kV backbone, while TAQA Distribution supplies customers at lower voltages. As subsidiaries of the same group, they can share data and align investment more easily, avoiding the split incentives seen in some liberalised markets.

‍

‍

‍

9 | Which region is best at sequencing grid investment with new renewables?

Abu Dhabi is doing best so far, because its largest new solar project is designed with storage from the outset.

Britain is building the Eastern Green Links to carry Scottish wind power south, but the links arrive between 2029 and 2035 (Table 1).

Australia built renewables ahead of transmission and is now retrofitting, for example with the Waratah battery, while VNI West's timetable slips. Transgrid's latest position on the New South Wales section is:

‍

We currently anticipate a decision on project approval in late 2026.

Transgrid, on the New South Wales section of VNI West, VNI West project page, accessed September 2026.

‍

That is what lagged sequencing costs: retrofits such as Waratah, and new lines that arrive years after the generation they serve.

‍

10 | Are grid regulations keeping pace with flexibility and storage?

Not yet: each region is reforming its rules, but none has finished.

In Britain, connection reform and the distribution system operation incentive in Ofgem's current distribution price control (RIIO-ED2), which rewards companies for using flexibility instead of reinforcement, show progress. But developers still wait years to connect: when Ofgem approved the reforms in April 2025, it found waiting times too long, with some new connection offers dated in the 2040s.

Ofgem now also funds grid expansion, partly to cut constraint costs:

‍

This investment (£52) alone is expected to lead to around £80 of savings for consumers by 2031 compared to not investing by reducing constraint costs (money paid to wind farms to switch off because the grid is unable to transmit their power output) and making better use of our clean renewable energy so we are not having to pay for expensive gas plants to serve demand.

Ofgem, on grid expansion in its draft transmission price control, draft settlement announcement, 1 July 2025.

‍

Abu Dhabi has moved from a pilot to a policy target of 200 MW of contracted demand response by 2030.

Australia's rule changes on wholesale demand response (2020) and integrating energy storage (2021) opened the market to flexible load and storage, but the wholesale mechanism remains little used (Figure 4) and local planning hurdles remain.

‍

‍11 | How can utilities and regulators plan the future grid together?

They can plan on shared scenarios and fund infrastructure jointly.

Joint scenario planning, such as the distribution scenarios built with NESO and AEMO's inputs and scenarios report, gives everyone the same evidence base.

Co-funded programmes, such as NESO's Stability Pathfinder and the AED 36 billion programme agreed by EWEC, TAQA and Masdar in April 2025, a quarter of it for grid, show how costs and risks can be shared.

Building social licence into planning, as AEMO now does, earns public trust and speeds up delivery.

‍

‍

‍

12 | Can Gulf states run a 100% renewable grid without hydropower, and what is missing?

Not yet: in MCC's assessment, about 90% renewables looks feasible, but the last 10% is still difficult and expensive.

Large-scale solar with multi-hour batteries, such as the Masdar and EWEC project, covers daily balancing. Dubai's pumped-storage plant at Hatta, targeted for completion in 2025, brings a technology new to the region:

‍

It is the first project of its kind in the Arabian Gulf region, with an investment of AED 1.421 billion. The project is expected to be fully completed by the end of the second quarter of 2025.

Dubai Electricity and Water Authority, on the Hatta pumped-storage plant, progress update, November 2024.

‍

Gas turbines able to co-fire green hydrogen remain the seasonal back-up.

The remaining gaps are inertia services and storage lasting more than 12 hours. The large Saudi battery awards so far are four- to five-hour systems, such as the 2.5 GW / 12.5 GWh the Saudi Electricity Company awarded in January 2025.

‍

References

‍

  1. Akaysha Energy. (n.d.). Waratah Super Battery. https://community.akayshaenergy.com/waratah-super-battery
  2. Alan Turing Institute. (n.d.). Towards a greener grid. https://www.turing.ac.uk/about-us/impact/towards-greener-grid
  3. Ampere Labs. (2024). Q1 2024 WEM review. https://amperelabs.com.au/wem-quarterly-market-review-q1-2024/
  4. Australian Energy Market Commission. (2020, June 11). Wholesale demand response mechanism [Rule change]. https://www.aemc.gov.au/rule-changes/wholesale-demand-response-mechanism
  5. Australian Energy Market Commission. (2021, December 2). Integrating energy storage systems into the NEM: Final determination. https://www.aemc.gov.au/sites/default/files/2021-12/1._final_determination_-_integrating_energy_storage_systems_into_the_nem.pdf
  6. Australian Energy Market Commission. (2024, December 19). Integrating price-responsive resources into the NEM [Rule change]. https://www.aemc.gov.au/rule-changes/integrating-price-responsive-resources-nem
  7. Australian Energy Market Operator. (2024). 2024 Wholesale Electricity Market Electricity Statement of Opportunities. https://www.aemo.com.au/-/media/files/electricity/wem/planning_and_forecasting/esoo/2024/2024-wem-electricity-statement-of-opportunities.pdf?rev=d18be34e317542c8b4da4c33baee1a47&sc_lang=en
  8. Australian Energy Market Operator. (2024). 2024 WEM ESOO data register [Data set]. https://www.aemo.com.au/-/media/files/electricity/wem/planning_and_forecasting/esoo/2024/2024-wem-esoo-data-register.xlsx?rev=16b00ee9ccb34264970f906f76e89659&sc_lang=en
  9. Australian Energy Market Operator. (2024). Quarterly energy dynamics Q1 2024. https://www.aemo.com.au/-/media/files/major-publications/qed/2024/qed-q1-2024.pdf
  10. Australian Energy Market Operator. (2024). Quarterly energy dynamics Q4 2024. https://www.aemo.com.au/-/media/files/major-publications/qed/2024/qed-q4-2024.pdf
  11. Australian Energy Market Operator. (2025, August). 2025 electricity network options report. https://www.aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2025/2025-electricity-network-options-report/final/2025-electricity-network-options-report.pdf
  12. Australian Energy Market Operator. (2025, June). 2025 Wholesale Electricity Market Electricity Statement of Opportunities. https://www.aemo.com.au/-/media/files/electricity/wem/planning_and_forecasting/esoo/2025/2025-wem-electricity-statement-of-opportunities.pdf
  13. Australian Energy Market Operator. (2025, May). Draft 2025 electricity network options report. https://www.aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2025/2025-electricity-network-options-report/draft-2025-electricity-network-options-report.pdf
  14. Australian Energy Market Operator. (2025, May). AEMO publishes electricity network options report for consultation [News update]. https://www.aemo.com.au/newsroom/news-updates/aemo-publishes-electricity-network-options-report-for-consultation
  15. Australian Energy Market Operator. (2025, May). Quarterly energy dynamics Q1 2025. https://www.aemo.com.au/-/media/files/major-publications/qed/2025/qed-q1-2025.pdf
  16. Australian Energy Market Operator. (2026). Quarterly energy dynamics Q1 2026. https://www.aemo.com.au/-/media/files/major-publications/qed/2026/qed-q1-2026.pdf
  17. Australian Energy Market Operator. (2026). Integrating price responsive resources into the NEM (IPRR). https://www.aemo.com.au/initiatives/major-programs/nem-reform-program/nem-reform-program-initiatives/integrating-price-responsive-resources-into-the-nem
  18. Australian Energy Market Operator. (2026, June). 2026 Integrated System Plan. https://www.aemo.com.au/energy-systems/major-publications/integrated-system-plan-isp/2026-integrated-system-plan-isp
  19. Australian Energy Market Operator. (2026, June 23). 2026 Wholesale Electricity Market Electricity Statement of Opportunities. https://www.aemo.com.au/-/media/files/electricity/wem/planning_and_forecasting/esoo/2026/2026-wem-electricity-statement-of-opportunities.pdf?rev=3aa69153c92f4437ac7032402a261f9c&sc_lang=en
  20. Australian Energy Regulator. (2025, August 28). Transparency review of AEMO's 2025 inputs, assumptions and scenarios report. https://www.aer.gov.au/publications/reports/performance/transparency-review-aemo-2025-inputs-assumptions-and-scenarios-report
  21. Department of Climate Change, Energy, the Environment and Water (New South Wales). (2025). NSW transmission planning review 2025. https://www.energy.nsw.gov.au/nsw-plans-and-progress/regulation-and-policy/nsw-transmission-planning-review-2025
  22. Department of Energy, Abu Dhabi. (2025, May). DoE launches second phase of demand response pilot project in collaboration with Energy Pool. https://www.doe.gov.ae/Media-Centre/News/DoE-launches-second-phase-of-demand-response-pilot-project-in-collaboration
  23. Department of Transport and Planning (Victoria). (n.d.). Victoria to New South Wales Interconnector West: Victorian component referral. https://www.planning.vic.gov.au/environmental-assessments/browse-projects/referrals/victoria-to-new-south-wales-interconnector-west-victorian-component
  24. Dubai Electricity and Water Authority. (2024, November). DEWA's hydroelectric power plant in Hatta. https://www.dewa.gov.ae/en/about-us/media-publications/latest-news/2024/11/dewas-hydroelectric-power-plant
  25. Electrical Review. (2026, June 1). National Grid opens consultation on Eastern Green Link 5 proposals. https://electricalreview.co.uk/2026/06/01/national-grid-opens-consultation-on-eastern-green-link-5-proposals/
  26. Enerdata. (2026, March). NKT secures deal for 2 GW Eastern Green Link 3 HVDC cable in the UK. https://www.enerdata.net/publications/daily-energy-news/nkt-secures-deal-2-gw-eastern-green-link-3-hvdc-cable-uk.html
  27. EnergyCo. (n.d.). Waratah Super Battery project. https://www.energyco.nsw.gov.au/our-projects/waratah-super-battery-project
  28. ESS News. (2025, January 13). Saudi Electricity Company awards 12.5 GWh battery storage contracts to China's BYD. https://www.ess-news.com/2025/01/13/saudi-electricity-company-awards-12-5-gwh-battery-storage-contracts-to-chinas-byd/
  29. ESS News. (2025, October 27). Masdar and EWEC break ground on 1 GW baseload solar-plus-storage project. https://www.ess-news.com/2025/10/27/masdar-ewec-break-ground-on-1-gw-baseload-solar-plus-storage-project/
  30. GOV.UK. (2023). Offshore Transmission Network Review. https://www.gov.uk/government/groups/offshore-transmission-network-review
  31. Independent review panel. (2025, June 27). NSW transmission planning review: Interim report. https://www.energy.nsw.gov.au/sites/default/files/2025-06/nsw-transmission-planning-review-interim-report.pdf
  32. Linxon. (2025, February). Linxon awarded new 400 kV grid station for the Industrial City of Abu Dhabi (ICAD) [Press release]. https://linxon.com/press-release-linxon-awarded-new-400-kv-grid-station-for-industrial-city-of-abu-dhabi-icad/
  33. Masdar. (2024, April). EWEC announces partners to develop solar project in Abu Dhabi. https://masdar.ae/en/news/newsroom/ewec-announces-partners-to-develop-solar-project-in-abu-dhabi
  34. Masdar. (2025, January). UAE President witnesses launch of the world's first 24/7 solar PV and battery storage project. https://masdar.ae/en/news/newsroom/uae-president-witnesses-launch-of-worlds-first-24-7-solar-pv-battery-storage
  35. Masdar. (n.d.). Round-the-clock project. https://masdar.ae/en/renewables/our-projects/rtc
  36. Masdar. (n.d.). World's largest solar power plants launched by EWEC. https://masdar.ae/en/news/newsroom/worlds-largest-solar-power-plants-launched-by-ewec
  37. Money Saving Expert. (2026, January). Demand Flexibility Service: Get paid to cut energy use. https://www.moneysavingexpert.com/utilities/cut-energy-demand-flexibility-service/
  38. National Energy System Operator. (2023, August). Demand Flexibility Service winter 2022/23 review. https://www.neso.energy/document/287006/download
  39. National Energy System Operator. (2025, April). NESO prepared for lowest ever electricity demand: 2025 Summer Outlook. https://www.neso.energy/neso-prepared-lowest-ever-electricity-demand-2025-summer-outlook
  40. National Energy System Operator. (2025, December 8). NESO implements electricity grid connection reforms to unlock investment in Great Britain. https://www.neso.energy/neso-implements-electricity-grid-connection-reforms-unlock-investment-great-britain
  41. National Energy System Operator. (2025, January). Next steps in grid connections reform. https://www.neso.energy/news/next-steps-grid-connections-reform
  42. National Energy System Operator. (2026). Summer Outlook 2026. https://www.neso.energy/document/380251/download
  43. National Energy System Operator. (n.d.). Demand Flexibility Service delivers electricity to power 10 million households. https://www.neso.energy/news/demand-flexibility-service-delivers-electricity-power-10-million-households
  44. National Energy System Operator. (n.d.). Dynamic Reserve Setting innovation project seeks to reduce balancing costs. https://www.neso.energy/news/dynamic-reserve-setting-innovation-project-seeks-reduce-balancing-costs
  45. National Energy System Operator. (n.d.). Former DeepMind experts' AI tool could help boost solar forecasts. https://www.neso.energy/news/former-deepmind-experts-ai-tool-could-help-boost-national-grid-esos-solar-forecasts
  46. National Grid. (2026, March). Major grid contracts signed to deliver the UK's biggest electricity transmission project, Eastern Green Link 3 [Press release]. https://nationalgrid-newsroom.prgloo.com/news/major-grid-contracts-signed-to-deliver-the-uks-biggest-electricity-transmission-project-eastern-green-link-3
  47. National Grid Electricity Distribution. (2025, January). Future Energy Scenarios will guide network development. https://www.nationalgrid.co.uk/news-and-events/latest-news/future-energy-scenarios-will-guide-network-development
  48. National Wealth Fund. (2025, May). National Wealth Fund backs ScottishPower to boost UK grid upgrades. https://www.nationalwealthfund.org.uk/news-and-publications/news/national-wealth-fund-backs-scottish-power-to-boost-uk-grid-upgrades/
  49. National Wealth Fund. (2026, March). ScottishPower secures £600m National Wealth Fund green financing for a strategic UK subsea power link, Eastern Green Link 4. https://www.nationalwealthfund.org.uk/news-and-publications/news/scottishpower-secures-600m-national-wealth-fund-green-financing-for-strategic-uk-subsea-power-link-eastern-green-link-4/
  50. New South Wales Government. (2025). 2025-26 Budget papers: Energy and climate change. https://www.nsw.gov.au/business-and-economy/nsw-budget/2025-26-budget-papers/our-plan-for-nsw/building-a-better-nsw/energy-and-climate-change
  51. Ofgem. (2025, April 15). Summary decision document: TMO4+ package. https://www.ofgem.gov.uk/sites/default/files/2025-04/Summary-Decision-Document-TMO4-package.pdf
  52. Ofgem. (2025, July 1). Ofgem approves initial £24 billion to operate and maintain critical gas networks and upgrade Britain's electricity supergrid [Press release]. https://www.ofgem.gov.uk/press-release/ofgem-approves-initial-ps24-billion-operate-and-maintain-critical-gas-networks-and-upgrade-britains-electricity-supergrid
  53. Ofgem. (2025, September). Distribution System Operation incentive report 2024/25. https://www.ofgem.gov.uk/sites/default/files/2025-09/DSO_Incentive_Report_2024_25_V1.pdf
  54. pv magazine Australia. (2023, May 29). Minister provides stamp of approval for VNI West powerline plan. https://www.pv-magazine-australia.com/2023/05/29/minister-provides-stamp-of-approval-for-vni-west-powerline-plan/
  55. Saudi Gulf Projects. (2025, February). Linxon awarded 400 kV substation in UAE. https://www.saudigulfprojects.com/2025/02/linxon-awarded-400-kv-substation-in-uae/
  56. SSEN Transmission. (n.d.). Eastern Green Link 3. https://www.ssen-transmission.co.uk/projects/project-map/eastern-green-link-3/
  57. SSEN Transmission. (n.d.). Eastern Green Link 5. https://www.ssen-transmission.co.uk/projects/project-map/eastern-green-link-5/
  58. Sunsave. (n.d.). The Demand Flexibility Service explained. https://www.sunsave.energy/blog/demand-flexibility-service
  59. TAQA Transmission. (2025). [News release on the formation of TAQA Distribution]. https://taqatransmission.com/node/111
  60. TAQA Transmission. (2025, April). [News release on the EWEC, TAQA and Masdar infrastructure programme]. https://taqatransmission.com/node/121
  61. TAQA Transmission. (n.d.). Our portfolio. https://taqatransmission.com/our-portfolio
  62. TAQA Transmission. (n.d.). Who we are. https://taqatransmission.com/who-we-are
  63. Tech Times. (2026, September 7). Rebuilt transformer energized: Waratah, Australia's largest battery, nears full capacity. https://www.techtimes.com/articles/326903/20260907/rebuilt-transformer-energized-waratah-australias-largest-battery-nears-full-capacity.htm
  64. Transgrid. (n.d.). VNI West. https://www.transgrid.com.au/projects-innovation/vni-west/
  65. WattClarity. (2026, June 25). AEMO releases the 2026 Integrated System Plan. https://wattclarity.com.au/articles/2026/06/25june-aemo-2026isp/
  66. Which?. (n.d.). Here's how to get rewards for using less electricity during peak-hour sessions this winter. https://www.which.co.uk/news/article/heres-how-to-get-rewards-for-using-less-electricity-during-peak-hour-sessions-this-winter-am6tu2m6tRaM
  67. Wärtsilä. (2025, March 3). Now operational: Wärtsilä delivers first-of-its-kind energy storage system for Zenobē in Scotland. https://www.wartsila.com/media/news/03-03-2025-now-operational-wartsila-delivers-first-of-its-kind-energy-storage-system-for-zenob%C4%93-in-scotland-3558119
  68. Zawya. (2025, September). Abu Dhabi DoE reports strong progress in 2025 demand response aggregator project. https://www.zawya.com/en/projects/utilities/abu-dhabi-doe-reports-strong-progress-in-2025-demand-response-aggregator-project-bo7x9gnm
  69. Zawya. (2026, February). First solar panel installed at 1.5 GW Al Ajban solar PV IPP in Abu Dhabi. https://www.zawya.com/en/projects/utilities/first-solar-panel-installed-at-15gw-al-ajban-solar-pv-ipp-in-abu-dhabi-h92d78j9
  70. Zenobē. (2025). Blackhillock battery storage launch. https://www.zenobe.com/news-and-events/blackhillock-battery-storage-launch/

‍

Authors

‍

 What’s next

Featured

This paper has been published on following other platforms

No items found.

I was delighted that MCC's work was completed on time, and within budget, helping us deliver important changes and improvements, to the benefit of our stakeholders. ​ MCC's report is published on the CCC website.

- Bea Natzler
Team Leader at Climate Change Committee, UK

I am delighted to recommend MCC Economics. Specifically, I worked closely with PJ, who helped us with our Nuclear and CCUS projects. PJ helped us develop new policies and answer questions from our stakeholders. ​​His support helped us deliver important changes and improvements, to the benefit of our stakeholders.

- Gordon Hutcheson
Head of Nuclear Policy at Ofgem, UK

MCC Economics has helped us better understand the most important issues for our stakeholders, including: charges, shareholder returns, debt payments and inflation impacts.

- Leila N. Nasr
Section Head at Department of Energy, Abu Dhabi

I am delighted to recommend PJ and his team at MCC Economics. We've been working together on National Policy Statements to help meet net zero targets for 2030 and 2050. We initially appointed MCC Economics to support us on offshore wind consultation analysis and have recently reappointed MCC Economics to undertake a larger consultation analysis role across all sectors, including hydrogen, CCUS and networks. I can confirm that PJ and his team have shown excellent spreadsheet skills, alongside very good project management, planning and analysis skills, helping us deliver important changes, and continuous improvements, to the benefit of our stakeholders.

- Amy McHugh
Head of Environment in the Energy Infrastructure Planning Policy, UK

I am delighted to recommend PJ and his team from MCC Economics. They helped us with our price controls for Heathrow airport and for NATS (En Route) plc (the air traffic services provider). Specifically, the MCC team helped us deliver important changes and improvements to our financial models and supporting policy documents, to the benefit of our stakeholders.

- Dan Rock
Head of Corporate Finance at CAA, UK

I am delighted to confirm that I worked with PJ on a retail project in 2015. The project helped stakeholders understand electricity costs and charges. Specifically, the project helped us explain to stakeholders, internally and externally, why electricity charges differed across the regions (GB, NI & Ireland). PJ was a key member on the project team, which helped deliver changes and improvements in the understanding of energy retail.

- Kevin Shiels
Director at Utility Regulator, Northern Ireland