RIIO-ED1 (2015 to 2023): Ofgem's First RIIO Price Control

Quick View

RIIO-ED1 was the first electricity distribution price control set under Ofgem's RIIO model, in which revenue is built from incentives, innovation and outputs. It ran for eight years, from 1 April 2015 to 31 March 2023, twice the length of every previous control. Western Power Distribution's four licensees were fast-tracked in February 2014 on the strength of their business plans, and the final determinations for the remaining ten companies followed on 28 November 2014. Ofgem set a cost of equity of 6.0% for the slow-track companies, indexed the cost of debt for the first time, and allowed £17.5 billion of total expenditure for the ten slow-track companies, cutting allowed revenues by about 4.7% on average against the previous control and taking roughly £12 off the typical annual household bill.

Key takeaways

‍

  • RIIO-ED1 applied the RIIO framework, the outcome of Ofgem’s RPI-X@20 review, to electricity distribution for the first time: an eight-year period, revenues tied to defined outputs, total expenditure allowances, and a fast-track route for high quality business plans.
  • Only Western Power Distribution cleared the fast-track hurdle. Its settlement was concluded in February 2014, with a cost of equity of 6.4% and an estimated financial benefit of around £250 million, and its customers’ distribution charges fell by 13.9%, about £13.50, in 2015-16.
  • Following the Competition Commission’s provisional determination for Northern Ireland Electricity, Ofgem cut the slow-track cost of equity to 6.0%, giving greater weight to current market conditions.
  • The cost of debt was indexed for the first time, using a trailing average of iBoxx bond yields that extends by one year each year from a ten-year starting point, so allowances track market interest rates rather than a fixed five-year guess.
  • Slow-track total expenditure allowances were £17.5 billion in 2012-13 prices, 7% below the companies’ final plans and 11% below their original fast-track plans, after allowances were set 75% on Ofgem’s view and 25% on the companies’ own forecasts.
  • Regulatory asset lives for new investment were extended from 20 to 45 years, transitioned over the eight-year period, aligning cost recovery with the economic life of the assets.
  • Allowed revenues fell by around 4.7% on average against DPCR5, an underlying reduction of about £12 in the typical annual household bill.
  • The control ultimately delivered strong reliability and near-universal output delivery, but at returns the National Audit Office judged higher than necessary, averaging around 9% in real terms. Those findings reshaped the following controls.

Scope of this article

‍

This article covers the review that set Great Britain’s electricity distribution price controls for 2015 to 2023, known as RIIO-ED1. It follows the fifth article in this series, on the 2009 review, and will be followed by an article on RIIO-ED2. It draws primarily on Ofgem’s final determinations overview of November 2014, the equity market return decision of February 2014 and the fast-track decision letter, with the retrospective assessment drawn from the National Audit Office’s 2020 report on electricity networks.

‍

‍

Table 1: How the review unfolded, October 2010 to April 2015

‍

DateStep
October 2010 Ofgem's RPI-X@20 review concluded, adopting the RIIO model for future network price controls.
March 2013 Strategy decision set the outputs, incentive framework and financial parameters for RIIO-ED1.
1 July 2013 The fourteen distribution network operators submitted and published their business plans.
22 November 2013 Ofgem published its assessment of the plans and proposed to fast-track Western Power Distribution.
17 February 2014 Equity market return decision: the reference cost of equity cut by 0.3 percentage points to 6.0%.
28 February 2014 Decision to fast-track Western Power Distribution's four licensees.
March 2014 The ten slow-track companies submitted revised plans, £700 million below their first plans.
July 2014 Draft determinations for the slow-track companies published for consultation.
28 November 2014 Final determinations for the ten slow-track companies, with a corrections letter on 17 December.
1 April 2015 The eight-year RIIO-ED1 price control took effect, running to 31 March 2023.

Sources: Ofgem RIIO-ED1 decision documents, 2013 to 2014.

What is RIIO, and where did it come from?

‍

RIIO stands for Revenue = Incentives + Innovation + Outputs. Ofgem’s RPI-X@20 project settled on it in 2010, after asking whether the regulatory model in place since privatisation could carry the sector through decarbonisation. The core of RPI-X survived, with multi-year revenue caps, a regulatory asset base, a cost of capital and strong efficiency incentives, the machinery this series has traced from the 1995 review onwards. The packaging changed. Controls would run for eight years instead of five. Revenues would be tied explicitly to output commitments across safety, reliability, the environment, connections, customer service and social obligations. Operating and capital expenditure would be assessed together as total expenditure, completing the journey DPCR5 began with its equalised incentives. Companies producing well-justified business plans could be fast-tracked, settling their control early on the plan as submitted.

RIIO-ED1 was the first application of this model to electricity distribution, covering the same fourteen licensees as DPCR5, by then held in six ownership groups.

‍

Why was Western Power Distribution fast-tracked, and what did it gain?

‍

The fast-track offer was designed to change behaviour before a single number was set, since the prospect of early settlement and lighter scrutiny pushed every company to sharpen its plan. Ofgem judged that the possibility inspired all the companies to raise their game, but only Western Power Distribution’s four licensees cleared the hurdle, and their price control was concluded in February 2014 on the plans as submitted, subject to one change described below. Ofgem estimated the distribution element of bills for Western Power Distribution’s customers, nationally about 19% of an average annual electricity bill, would fall by 13.9% in 2015-16, around £13.50 in 2012-13 prices.

Fast-tracking was worth having. Ofgem later calculated the financial benefit to the company at around £250 million, since a fast-tracked plan is accepted rather than benchmarked down, and the company kept the original fixed ten-year cost of debt index design rather than the revised version applied to the others. Ofgem defended the asymmetry openly in the final determinations: the fast-track process had produced better initial business plans across the sector, a further £700 million of reductions between the first and revised slow-track plans, and better benchmarking data, benefits it judged greater than the advantage to the fast-tracked company.

‍

How was the cost of equity set at 6 per cent?

‍

The cost of equity decision arrived in two steps, and an appeal in a different jurisdiction forced the second. Ofgem’s central reference point for assessing the plans was 6.3%, against the 6.7% the companies had themselves proposed. In November 2013 the Competition Commission published its provisional determination for Northern Ireland Electricity, giving materially more weight to current market evidence on equity returns than British energy regulation had done. Ofgem consulted, and in February 2014 decided to give greater weight to current market conditions, cutting its central reference point for the cost of equity to 6.0%, a reduction of 0.3 percentage points from the figure used in the business plan assessment. Western Power Distribution accepted a 0.3 point reduction of its own, to 6.4%, as the condition of staying fast-tracked, which brought its opening weighted average cost of capital to 3.9%.

The debt side changed more fundamentally. DPCR5 had fixed the cost of debt allowance for five years, and falling interest rates turned that fixed allowance into a significant source of outperformance for the companies. Under RIIO-ED1 the allowance is calculated each year from a trailing average of iBoxx non-financial corporate bond yields of ten years and over, deflated by implied inflation, with the averaging window extending by one year each year from a ten-year starting point. This trombone design largely removed the sector’s exposure to interest rate uncertainty in either direction.

‍

‍

Figure 1: The allowed cost of equity from DPCR4 to RIIO-ED1, post-tax real at the notional gearing of each review

‍

‍

The chart shows the allowed post-tax real cost of equity for electricity distribution falling across three successive price controls. It fell by 0.8 percentage points between DPCR4 and DPCR5, reflecting the lower interest rate environment following the 2008 financial crisis. It then fell again in RIIO-ED1, reaching 6.4% for the four Western Power Distribution licensees that were fast-tracked in February 2014, and 6.0% for the remaining ten slow-track companies settled in November 2014.

The teal bars cover the two controls set under the old RPI-X framework, where the cost of equity was negotiated as a fixed point for the full five-year period. The orange bars mark the transition to RIIO, where Ofgem introduced a market-indexed cost of debt alongside the fixed equity allowance. The 0.4 percentage point gap between fast-track and slow-track reflects the reward Ofgem offered for companies willing to submit high-quality business plans and accept an early settlement.

‍

How did Ofgem assess efficient expenditure?

‍

Expenditure was assessed on a total expenditure basis for the first time, using three benchmarking models: a top-down model with high-level cost drivers, a bottom-up model built from disaggregated activity drivers, and a fully disaggregated activity-level assessment, weighted 25%, 25% and 50% respectively. Companies were benchmarked against the upper quartile, and each company’s allowance was then set by interpolation, 75% on Ofgem’s view of efficient cost and 25% on the company’s own forecast, with the information quality incentive giving companies that forecast closer to Ofgem’s view a stronger efficiency incentive rate.

Three adjustments did most of the work on the slow-track plans. The comparative cost assessment identified over £700 million of scope for reduction. Ofgem’s view of the savings available from smart grid solutions, beyond the £476 million the companies had already included, removed a further £322 million. And an updated assessment of real price effects, the expected movement of network input costs relative to inflation, came in £728 million below the companies’ forecasts. The result was a final slow-track allowance of £17.5 billion in 2012-13 prices, 7% below the companies’ revised plans and 11% below their original submissions.

‍

‍

Figure 2: Slow-track total expenditure by company: submitted plans, Ofgem’s view of efficient costs and final allowances after interpolation, in 2012-13 prices

‍

‍

Each of the three bars in the chart represents a different view of how much each company should be allowed to spend. The grey bar is what the company asked for in its business plan. The teal bar is Ofgem's independent assessment of what an efficient operator would need, invariably lower, reflecting the regulator's cost benchmarking. The orange bar is the final allowance actually set.

The final allowance is not simply Ofgem's figure. It is derived by a 75/25 interpolation: 75% of the weight goes to Ofgem's efficiency view, and 25% to the company's own plan. The result sits closer to Ofgem's number than to the company's, but the company retains some influence over its own settlement. This sharing mechanism was designed to protect companies from being penalised by benchmarking error while still giving them an incentive to submit realistic, well-evidenced plans. Where the grey and teal bars are far apart, as they are for EPN and SPMW, the orange allowance falls well below what the company requested.

‍

What outputs did the companies have to deliver?

‍

The output framework was RIIO’s defining feature, tying revenue to commitments the companies had to meet rather than to costs alone. The interruptions incentive scheme continued to reward and penalise performance on the number and duration of power cuts against company-specific targets. A broad measure of customer service combined a satisfaction survey, a complaints metric and an assessment of stakeholder engagement, and a time-to-connect incentive covered smaller connections. On the environment, losses moved from a troubled financial incentive to a licence requirement to keep losses as low as reasonably practicable, supported by published losses strategies, while companies reported their business carbon footprint. Innovation funding continued through the Network Innovation Allowance and an annual Network Innovation Competition, the successors to the Low Carbon Networks Fund described in the previous article.

The financial arrangements changed to match the longer horizon. Regulatory asset lives for new additions were extended from 20 to 45 years, phased over the eight-year period, so that customers pay for assets across something closer to their economic life, and capitalisation rates of between 64% and 80% determined how much of each company’s expenditure entered the asset base rather than being recovered in-year.

‍

‍

Table 2: The RIIO-ED1 financial package against DPCR5

‍

Component DPCR5 (2010 to 2015) RIIO-ED1 (2015 to 2023)
Cost of equity (post-tax real) 6.7% 6.0% slow-track; 6.4% fast-track
Cost of debt Fixed at 3.6% for five years Indexed: trailing average of iBoxx yields, extending from ten years
Notional gearing 65% 65%
Regulatory asset lives (new additions) 20 years 45 years, transitioned over eight years
Capitalisation rate 85% of relevant expenditure 64% to 80%, by company
Period Five years Eight years

Source: Ofgem, RIIO-ED1 Final Determinations Overview, November 2014, Table 5.1.

‍

What did the settlement mean for customers?

‍

The headline effect was a reduction. Allowed revenues fell by around 4.7% on average over RIIO-ED1 relative to the final year of DPCR5, an underlying reduction of about £12 in the typical annual household bill, while the ten slow-track companies were still able to spend £17.5 billion renewing, maintaining and operating the networks. Base revenues for the ten slow-track companies totalled £28.5 billion over the eight years in 2012-13 prices. Ofgem’s return on regulatory equity analysis, the tool introduced at DPCR5, indicated that outperforming companies could earn equity returns above 10% while underperformers could fall below the cost of debt, a deliberately wide range intended to make the incentives bite.

‍

How did RIIO-ED1 turn out?

‍

Operationally, it delivered. The National Audit Office’s January 2020 review of electricity networks found that consumers in Great Britain experienced fewer power cuts than in most other European Union countries and that the network companies had met almost all of their targets across safety, the environment, reliability, connections, customer service and support for vulnerable consumers. Ofgem’s own annual reports on the control tracked most companies earning rewards on reliability and customer service, with customers benefiting directly from the improved performance.

Financially, the verdict was harsher. The National Audit Office found the network companies on course for shareholder returns of around 9% in real terms against a United Kingdom company average of around 5% to 6%, with about 1.5 percentage points coming from incentive rewards against targets that were in some cases already being beaten before the control began, and about 1.2 percentage points from spending below allowances. It estimated that consumers could have paid at least £800 million less had Ofgem placed more weight on up-to-date evidence about network company risk, and it criticised the eight-year length for locking in the settlement too long. Ofgem’s response acknowledged that overall costs to consumers had turned out higher than necessary, noting that over £6 billion had been shared back with customers across the networks through the sharing mechanisms and voluntary contributions, and pointing to the tougher settlements then in preparation.

RIIO-ED1 repeated the oldest pattern in this series. A control calibrated on cautious assumptions about risk and cost was outperformed by companies that turned out to be safer and cheaper to run than assumed. The 1990 controls taught that lesson first, as the opening article described. RIIO-ED1 taught it again, and its successors answered. The RIIO-2 controls and RIIO-ED2 cut allowed equity returns substantially and returned to five-year periods. That review is the subject of the next article in this series.

‍

‍

References

‍

  1. Ajayi, V., Anaya, K., & Pollitt, M. G. (2021). Incentive regulation, productivity growth and environmental effects: The case of electricity networks in Great Britain (Working Paper No. 012). The Productivity Institute.
  2. National Audit Office. (2020). Electricity networks (HC 42, Session 2019-20). National Audit Office. https://www.nao.org.uk/reports/electricity-networks/
  3. Ofgem. (2013). Strategy decision for the RIIO-ED1 electricity distribution price control: Overview. Office of Gas and Electricity Markets.
  4. Ofgem. (2014a). Decision on our methodology for assessing the equity market return for the purpose of setting RIIO-ED1 price controls. Office of Gas and Electricity Markets.
  5. Ofgem. (2014b). Decision to fast-track Western Power Distribution [Open letter, 28 February 2014]. Office of Gas and Electricity Markets.
  6. Ofgem. (2014c). RIIO-ED1: Draft determinations for the slow-track electricity distribution companies – Overview. Office of Gas and Electricity Markets.
  7. Ofgem. (2014d). RIIO-ED1: Final determinations for the slow-track electricity distribution companies – Overview. Office of Gas and Electricity Markets.
  8. Ofgem. (2014e). RIIO-ED1: Final determinations for the slow-track electricity distribution companies – Business plan expenditure assessment. Office of Gas and Electricity Markets.
  9. Ofgem. (2014f). RIIO-ED1 slow-track final determinations: Analyst and investor presentation. Office of Gas and Electricity Markets.
  10. Ofgem. (2017). Guide to the RIIO-ED1 electricity distribution price control. Office of Gas and Electricity Markets.
  11. Ofgem. (2020). Ofgem responds to National Audit Office report on electricity networks [Press release]. Office of Gas and Electricity Markets.
  12. Ofgem. (2023). RIIO-ED1 network performance summary 2021-22. Office of Gas and Electricity Markets.

‍

Authors

‍

 What’s next

Featured

This paper has been published on following other platforms

No items found.

I was delighted that MCC's work was completed on time, and within budget, helping us deliver important changes and improvements, to the benefit of our stakeholders. ​ MCC's report is published on the CCC website.

- Bea Natzler
Team Leader at Climate Change Committee, UK

I am delighted to recommend MCC Economics. Specifically, I worked closely with PJ, who helped us with our Nuclear and CCUS projects. PJ helped us develop new policies and answer questions from our stakeholders. ​​His support helped us deliver important changes and improvements, to the benefit of our stakeholders.

- Gordon Hutcheson
Head of Nuclear Policy at Ofgem, UK

MCC Economics has helped us better understand the most important issues for our stakeholders, including: charges, shareholder returns, debt payments and inflation impacts.

- Leila N. Nasr
Section Head at Department of Energy, Abu Dhabi

I am delighted to recommend PJ and his team at MCC Economics. We've been working together on National Policy Statements to help meet net zero targets for 2030 and 2050. We initially appointed MCC Economics to support us on offshore wind consultation analysis and have recently reappointed MCC Economics to undertake a larger consultation analysis role across all sectors, including hydrogen, CCUS and networks. I can confirm that PJ and his team have shown excellent spreadsheet skills, alongside very good project management, planning and analysis skills, helping us deliver important changes, and continuous improvements, to the benefit of our stakeholders.

- Amy McHugh
Head of Environment in the Energy Infrastructure Planning Policy, UK

I am delighted to recommend PJ and his team from MCC Economics. They helped us with our price controls for Heathrow airport and for NATS (En Route) plc (the air traffic services provider). Specifically, the MCC team helped us deliver important changes and improvements to our financial models and supporting policy documents, to the benefit of our stakeholders.

- Dan Rock
Head of Corporate Finance at CAA, UK

I am delighted to confirm that I worked with PJ on a retail project in 2015. The project helped stakeholders understand electricity costs and charges. Specifically, the project helped us explain to stakeholders, internally and externally, why electricity charges differed across the regions (GB, NI & Ireland). PJ was a key member on the project team, which helped deliver changes and improvements in the understanding of energy retail.

- Kevin Shiels
Director at Utility Regulator, Northern Ireland